Projects
Project Clydesdale data center campus near Owasso
Unincorporated Tulsa County, Tulsa County
506 acres · for Google
🕒 Aug 20, 2026: Google said it is the company behind Project Clydesdale.
Being builtMeta "Project Anthem" data center in east Tulsa
Tulsa, Tulsa County
340 acres · for Meta
🕒 April 21, 2026: Meta announced it broke ground on its first Oklahoma data center, built for AI, worth mo…
Local votes and rules
⏸️ Pause on new data centers · Broken Arrow
Broken Arrow City Council voted unanimously for a six-month pause on accepting land use applications for data centers, ending December 31, 2026, with an option to extend six more months. It came after a deal for a 52-acre site in east Broken Arrow fell through.
⏸️ Pause on new data centers · Tulsa
Tulsa City Council voted unanimously to pause new data center construction permits for about nine months, through the end of 2026, while planners study noise, water, power and zoning. Phases 1 and 2 of Meta's Project Anthem can continue.
✅ Approved · Unincorporated Tulsa County
Tulsa County commissioners approved tax breaks for the Project Clydesdale data center west of Owasso. Ground was broken in October 2025; Google later said it is the company behind it.
Find your town
In Oklahoma, cities and towns decide inside their limits. Outside them, the county decides.