Cloverleaf "Project Open Sky" data center campus north of Piedmont
Also called: Project Open Sky, Cloverleaf data center
Cloverleaf Infrastructure wants Piedmont to annex and rezone about 633 acres for a large data center campus. After resident pushback, it cut on-site power plants and capped water use. The council has delayed its vote five times.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Piedmont City.
Where things stand: Proposed Planning Commission recommended approval 3-1 on Nov 12, 2026, with a 75,000-gallon daily water cap and noise limits. The City Council still has to vote.
- Oct 22, 2026: Piedmont, Canadian County: project approved Source
❓ 4 open questions about it: see below.
Last checked Nov 15, 2026.
🕒 Latest update (Nov 12, 2026): Piedmont's Planning Commission voted 3-1 to recommend that the City Council approve Cloverleaf's amended plan for Project Open Sky, with a water cap of 75,000 gallons a day, no wells, noise limits and a cultural artifacts study.
What we know
- 📍 WhereAbout 633 acres just north of Piedmont (developer also holds land options in Kingfisher County), Piedmont, Canadian County
- 🏢 CompanyCloverleaf Infrastructure
- 🌳 Size633 acres
- 🔌 Where the power comes fromRevised plan drops on-site gas plants, batteries and geothermal; power source otherwise not stated
- 💧 Water75,000 gallons a day
- ❄️ Coolingclosed-loop cooling
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts would the campus use, and where would the power come from? 🙋 I'll find out ·
- Which company would use the data center? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
- When will the Piedmont City Council vote on the Project Open Sky plan? 🙋 I'll find out ·
What happened so far
- Sept 2026Cloverleaf revised its plan: no on-site power plants, water capped at 75,000 gallons a day, closed-loop cooling, no water wells, noise monitoring.
- Sept 28, 2026City Council deadlocked 2-2 and the mayor broke the tie to delay the vote again, the fifth delay.
- Oct 22, 2026Piedmont City Council voted 4-1 to approve Cloverleaf's amended master design plan (about 633 acres, up to six buildings). An amendment requires Frisco Road to stay open, rerouted around the site. This is not final zoning approval.
- Nov 12, 2026Piedmont's Planning Commission voted 3-1 to recommend that the City Council approve Cloverleaf's amended plan for Project Open Sky, with a water cap of 75,000 gallons a day, no wells, noise limits and a cultural artifacts study.
Local votes and rules
🗺️ Zoning change
The Planning Commission voted 3-1 to recommend that the City Council approve Cloverleaf's amended plan (planned unit development) for Project Open Sky. This reverses its earlier advice to deny. Conditions include a cap of 75,000 gallons of water a day (except for firefighting), no water wells, noise limits of 60 decibels by day and 50 at night, and studies paid for by Cloverleaf, including a new study looking for Native American artifacts. The City Council still has to vote.
✅ Approved
City Council voted 4-1 to approve Cloverleaf's amended master design plan for its data center campus. It requires Frisco Road to stay open, rerouted around the site, and the developer to pay for studies. Rezoning hearings are still needed before final zoning approval.
🗺️ Zoning change
Cloverleaf asked Piedmont to rezone thousands of acres from farm use to a planned unit development for its Project Open Sky data center campus. The Planning Commission advanced it in June 2026. City Council has delayed its vote five times; on September 28 the mayor broke a 2-2 tie to delay again. In July the council refused to change the future land use map and sent it back to the Planning Commission.
📜 Data center rules
Piedmont City Council created a new Industrial Technology zoning district, a zone meant for uses like data centers.
Drag the slider to compare the land before and now.
Where this comes from
- 'You've dragged your feet': Piedmont delays data center vote for fifth time · News 9 · Sept 29, 2026
- What to know about Piedmont, Oklahoma's Project Open Sky Data Center · News 9 · Sept 18, 2026
- Piedmont delays vote on revised Cloverleaf data center plans · FOX 25 · Sept 2026
- Piedmont City Council again tables special zoning draft for Project Open Sky data center · OKCFox · Sept 28, 2026
- Piedmont City Council advances data center proposal · News 9 · Oct 22, 2026
- Piedmont advances second proposed data center as residents raise concerns · News 9 · Oct 27, 2026
- Piedmont Planning Commission backs moving Cloverleaf data center master plan to council · OKCFox (KOKH) · Nov 12, 2026