Project Thunderbird data center and gas power campuses (Enid)
Also called: Project Thunderbird, Plainsmen Holdings
A group of Enid natives proposes a $35 billion data center project on about 1,735 acres at four sites in and around Enid. It would make its own power with up to 3.3 gigawatts of gas plants and use Kaw Lake water. The City Commission approved three rezonings in October 2026; opponents are working on a recall and a petition for a public vote.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Enid City.
Where things stand: Approved, not built yet City Commission approved three rezonings 6-1 on Oct 27, 2026. This does not allow building yet; each data center still needs its own city review.
- Nov 1, 2026: Our records now list Project Thunderbird data center and gas power campuses (Enid) as approved Source
- Oct 27, 2026: Enid, Garfield County: project approved Source
❓ 6 open questions about it: see below.
Last checked Nov 1, 2026.
🕒 Latest update (Oct 30, 2026): The resident group No Data Centers in Enid said it started a recall effort against the mayor and several commissioners and is working on a petition to force a public vote to undo two of the rezonings.
What we know
- 📍 WhereFour sites: east-side city industrial park, north near Phillips Rd, west-central near 30th and Southgate, south near Southgate Rd, Enid, Garfield County
- 🏢 CompanyPlainsmen Holdings LLC
- 🌳 Size1,735 acres
- ⚡ Power it needs2,750 megawatts (about as much as 2,200,000 homes)
- 🔌 Where the power comes fromNew natural gas power plants on site (up to 3.3 GW), not relying on the regional grid
- 💧 WaterRaw water from the Kaw Lake pipeline
- ❄️ Coolingclosed-loop cooling
- 💵 Cost$35 billion
- 👷 Jobs promised600
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water would the campuses use per day? 🙋 I'll find out ·
- Which companies would use the data centers? 🙋 I'll find out ·
- What air permits would the gas plants need? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
- Will residents gather enough signatures to force a public vote on the rezonings? 🙋 I'll find out ·
- Has the developer reached a water deal with the City of Enid? 🙋 I'll find out ·
What happened so far
- Sept 28, 2026The Metropolitan Area Planning Commission recommended approving the rezoning.
- Oct 2026The City Commission moved the rezoning hearing from Oct 6 to a special meeting on Oct 27.
- Oct 27, 2026At a special meeting, the Enid City Commission voted 6-1 to approve three Project Thunderbird rezonings from farm to industrial use. A vote to make them take effect right away (an emergency clause) did not happen, so they take effect later.
- Oct 30, 2026The resident group No Data Centers in Enid said it started a recall effort against the mayor and several commissioners and is working on a petition to force a public vote to undo two of the rezonings.
Local votes and rules
🗳️ Public vote
After the rezoning vote, the resident group No Data Centers in Enid said it is working on a petition to force a public vote to undo two of the Project Thunderbird rezonings, and on recalls of the mayor and several commissioners. A referendum needs signatures equal to 25% of votes cast in the city election.
✅ Approved
At a special meeting, the City Commission voted 6-1 to approve three rezonings from farm to industrial use for Project Thunderbird. No commissioner moved to make them take effect right away. The city says this does not approve building or running a data center; each one needs separate review.
🗺️ Zoning change
On September 28, 2026, Enid's Metropolitan Area Planning Commission voted 6-1 and 5-2 to recommend the rezoning requests for Project Thunderbird. The City Commission moved its hearing from October 6 to a special meeting on October 27, 2026, at 5 p.m. at the Stride Bank Center Grand Ballroom, to fit more people.
Drag the slider to compare the land before and now.
Where this comes from
- Proposed Enid data center project could bring $35 billion investment · News 9 · Sept 2026
- UPDATED: Rezoning requests removed from agenda · Enid News & Eagle · Oct 2026
- Project Thunderbird · City of Enid
- Data center foes target city leaders for recall, seek to undo rezoning · Enid News & Eagle · Oct 30, 2026
- 5 things to know: early voting, data center developments · News 9 · Oct 28, 2026