Send us a tip
Approved, not built yetBig (AI-size): 600 acres

Meta data center in Piqua (Project Klondike)

Also called: J5 LLC, Shaytura LLC

Meta plans a $1 billion data center on about 600 acres in Piqua. The city approved it quickly in 2025 while officials were under an agreement to keep the plans private (NDA). Residents raised worries about water, noise and power bills.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Piqua City.

Where things stand: Approved, not built yet City approved the deal in November 2025 by emergency vote. In August 2026 Meta was named and the city approved a power deal with AES Ohio.

  • Nov 3, 2026: Piqua, Miami County: referendum decided Source

❓ 4 open questions about it: see below.

Last checked Nov 9, 2026.

🕒 Latest update (Nov 3, 2026): Piqua voters approved a charter ban on data centers over 25 megawatts, about 2 to 1, and recalled three city commissioners, including the mayor and vice mayor (unofficial results).

What we know

  • 📍 WhereField at Washington and Farrington roads, in Piqua's I-75 business park, near the Great Miami River, Piqua, Miami County
  • 🏢 CompanyJ5 LLC (also Shaytura LLC)
  • 🏛️ Owned byMeta Platforms
  • 👤 Built forMeta
  • 🌳 Size600 acres
  • 🔌 Where the power comes fromAES Ohio will supply power under an agreement the city approved in August 2026.
  • 💵 Cost$1 billion
  • 💸 Tax breaksA property tax break was approved with the project in November 2025. Meta also pledged $8 million for city fire trucks and police cars.
  • 🤐 Privacy agreement (NDA)Yes. City officials signed an agreement to keep the plans private (NDA) that kept the company's name hidden until August 2026.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will the Piqua data center use, and from which wells? 🙋 I'll find out ·
  • How many buildings and megawatts are planned? 🙋 I'll find out ·
  • What are the exact terms of the tax break? 🙋 I'll find out ·
  • Does the Nov. 3, 2026 charter ban affect the Meta data center the city already approved? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Nov 2025
      Piqua City Commission approved the project and a tax break by emergency resolution.
    • Aug 2026
      Meta was named as the company and pledged $8 million for city emergency equipment. The city approved a power deal with AES Ohio.
    • Nov 3, 2026
      Piqua voters approved a charter ban on data centers over 25 megawatts, about 2 to 1, and recalled three city commissioners, including the mayor and vice mayor (unofficial results).

    Local votes and rules

    🗳️ Public vote

    Voters approved a city charter change that bans data centers over 25 megawatts, about 2 to 1. The same day, voters recalled three city commissioners, including the mayor and vice mayor, who had approved the Meta data center. Results are unofficial until the county elections board certifies them (expected in late November 2026).

    Nov 3, 2026

    🗳️ Public vote

    Voters will decide a city charter change that would ban data centers that use more than 25 megawatts of power. Other petitions, including a full ban, are set for special elections. The city has approved steps for a planned Meta data center.

    Nov 3, 2026

    🤝 Agreement with the company

    City commission approved a 30-year agreement letting AES Ohio supply power to the planned Meta data center. Meta pledged $8 million for city fire and police equipment.

    Aug 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something