USA › Ohio › Miami County

Miami County

1 data center project we know about. 26 townships, villages and cities.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

Local votes and rules

🗳️ Public vote · Piqua

Voters approved a city charter change that bans data centers over 25 megawatts, about 2 to 1. The same day, voters recalled three city commissioners, including the mayor and vice mayor, who had approved the Meta data center. Results are unofficial until the county elections board certifies them (expected in late November 2026).

Nov 3, 2026Source

🗳️ Public vote · Piqua

Voters will decide a city charter change that would ban data centers that use more than 25 megawatts of power. Other petitions, including a full ban, are set for special elections. The city has approved steps for a planned Meta data center.

Nov 3, 2026Source

🤝 Agreement with the company · Piqua

City commission approved a 30-year agreement letting AES Ohio supply power to the planned Meta data center. Meta pledged $8 million for city fire and police equipment.

Aug 2026Source