Trammell Crow data center, Eldorado Valley
Trammell Crow got city approval for a 1.3 million square foot data center on 157 acres in Henderson's Eldorado Valley. In 2026 the land owner said the deal fell through and the land is being sold for regular industrial use.
Where things stand: Approved in Nov. 2025, but the deal fell through in 2026. Land being sold for other industry; permit still active.
๐ Latest update (March 2026): A real estate agent told the city the data center was no longer moving forward.
What we know
- ๐ WhereNE corner of Bentonite Avenue and Whidbey Road, Eldorado Valley, near US 95 and I-11, Henderson, Clark County
- ๐ข CompanyTrammell Crow Co.
- ๐ณ Size157 acres
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Could a new buyer still use the active data center permit before it expires in 2030? ๐ I'll find out
What happened so far
- Nov 2025Henderson Planning Commission approved a use permit for five buildings (about 1.3 million sq ft) and a substation.
- March 2026A real estate agent told the city the data center was no longer moving forward.
Local votes and rules
๐ Other
Henderson City Council decided not to adopt a proposed 180-day pause on data centers. Instead it told city staff to write tougher rules: any future data center would need its own negotiated contract with the city (a development agreement) covering water, power, noise, heat and distance from homes. The city said no data center applications were on file.
โ Approved
Henderson's Planning Commission approved a permit (conditional use permit and design review) for a Trammell Crow data center complex: five buildings on 157.3 acres at Bentonite Avenue and Whidbey Road in the Eldorado Valley. The approval lasts six years, to 2030. In March 2026 a real estate agent told the city the data center plan was no longer moving forward.
An aerial photo of the area.
Where this comes from
- Data Center Project No Longer Moving Forward in Henderson, Nev. ยท GovTech (Las Vegas Review-Journal) ยท Aug 3, 2026
- What steps are Southern Nevada leaders taking โ or not taking โ to regulate the growing data center industry? ยท KTNV ยท Sept 2026
See something wrong? Tell us and we'll fix it.