Approved, not built yetBig (AI-size): 1,880 acres

Google data center (county land near Hobbs, Lea County)

Google plans a data center on 1,880 acres of county-owned land on the edge of Hobbs. On Nov. 19, 2026, Lea County commissioners approved $130 billion in tax-break bonds and a lease. A 2-gigawatt solar field about 3 miles away would power it. Construction could start in 2027, with operations from mid-2029.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Where things stand: Approved, not built yet County commissioners approved $130 billion in tax-break bonds and a land lease on Nov. 19, 2026 (one commissioner voted no). Construction expected to start in 2027.

  • Nov 24, 2026: Our records now list Google data center (county land near Hobbs, Lea County) as approved Source
  • Nov 19, 2026: Lea County, Lea County: project approved Source

❓ 4 open questions about it: see below.

Last checked Nov 24, 2026.

🕒 Latest update (Nov 19, 2026): Lea County commissioners approved three ordinances for $130 billion in tax-break bonds and a lease of 1,880 acres of county land for the Google data center. One commissioner voted no. They also turned down a petition for a six-month pause on data centers.

What we know

  • 📍 WhereCounty-owned land on the outskirts of Hobbs, unknown, Lea County
  • 🏢 CompanyGoogle
  • 🏛️ Owned byAlphabet
  • 👤 Built forGoogle
  • 🌳 Size1,880 acres
  • 🔌 Where the power comes fromA 2-gigawatt solar field by Excelsior Energy about 3 miles away. Google says it will pay all power and grid costs.
  • 💧 WaterCity of Hobbs water system for daily operations; Google is seeking to buy water rights
  • ❄️ Coolingclosed-loop, non-evaporative cooling (planned)
  • 💸 Tax breaks$130 billion in industrial revenue bonds (a tax break). In return, news reports say Google pays $15.6 million a year in payments instead of taxes, $8.5 million per building a year for 30 years, and an $18 million housing fund.
  • 👷 Jobs promised125

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water would it use once running? 🙋 I'll find out ·
  • Where exactly on the edge of Hobbs is the 1,880-acre county site? 🙋 I'll find out ·
  • Can the county change the agreement with Google without a public commission vote? 🙋 I'll find out ·
  • Where will Google get the water rights it is seeking? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 14, 2026
      Google announced it is exploring a data center in Lea County and is talking with local officials.
    • Nov 19, 2026
      Lea County commissioners approved three ordinances for $130 billion in tax-break bonds and a lease of 1,880 acres of county land for the Google data center. One commissioner voted no. They also turned down a petition for a six-month pause on data centers.

    Local votes and rules

    ✅ Approved

    Lea County commissioners approved $130 billion in tax-break bonds (industrial revenue bonds) and a lease of 1,880 acres of county land near Hobbs for a Google data center. One commissioner voted no. The same night they turned down a petition with more than 800 signatures asking for a six-month pause on data centers.

    Nov 19, 2026

    📌 Other

    County commissioners agreed to consider more than $134 billion in tax-break bonds (industrial revenue bonds) for a Google data center with partner Excelsior: two large buildings on 1,890 acres of county-owned land, plus a solar field about 3 miles away. No final bond vote yet. The state Board of Finance must also review any county land sale.

    Sept 24, 2026

    📌 Other

    County commissioners unanimously passed a resolution with guidelines for data centers. Data centers on the public power grid must not raise rates for homes or businesses. Operators must publish yearly water use, split by use. Water-hungry evaporative cooling is not allowed.

    Feb 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Lea County, New Mexico · Google · Sept 14, 2026
    2. Google announces it is 'exploring' a potential data center in rural New Mexico county · Source NM · Sept 15, 2026
    3. Lea County Commission OKs $130 billion deal for Google data center · Searchlight New Mexico · Nov 20, 2026

    See something wrong? Tell us and we'll fix it.