Google data center (county land near Hobbs, Lea County)
unknown, Lea County
1,880 acres · for Google
🕒 Nov 19, 2026: Lea County commissioners approved three ordinances for $130 billion in tax-break bonds a…
ProposedNew Era Energy & Digital AI data center campus (near Caprock)
Unincorporated Lea County, Lea County
3,500 acres
🕒 Nov 6, 2025: New Era Energy & Digital announced a land option for about 3,500 acres for a 7 GW AI dat…
Local votes and rules
✅ Approved · Lea County
Lea County commissioners approved $130 billion in tax-break bonds (industrial revenue bonds) and a lease of 1,880 acres of county land near Hobbs for a Google data center. One commissioner voted no. The same night they turned down a petition with more than 800 signatures asking for a six-month pause on data centers.
📌 Other · Lea County
County commissioners agreed to consider more than $134 billion in tax-break bonds (industrial revenue bonds) for a Google data center with partner Excelsior: two large buildings on 1,890 acres of county-owned land, plus a solar field about 3 miles away. No final bond vote yet. The state Board of Finance must also review any county land sale.
📌 Other · Lea County
County commissioners unanimously passed a resolution with guidelines for data centers. Data centers on the public power grid must not raise rates for homes or businesses. Operators must publish yearly water use, split by use. Water-hungry evaporative cooling is not allowed.
Find your town
In New Mexico, cities and towns decide inside their limits. Outside them, the county decides.
Towns without a link have nothing reported yet. To see who decides there and your electric company, type your ZIP on the home page.
- Eunice City
- Hobbs City
- Jal City
- Lovington City
- Tatum Town
- Unincorporated Lea County