Being builtBig (AI-size): 1,400 acres

Project Jupiter data center campus (Santa Teresa)

Also called: Project Jupiter, Stargate New Mexico, Stargate Jupiter

A huge AI data center campus for Oracle and OpenAI on about 1,400 acres in Santa Teresa. It would make its own power from natural gas fuel cells. The county approved big tax breaks in 2025, and building has started, but the state air permit, a gas pipeline across state land, and water use are still being fought over.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Monday, December 7, 2026, 9:00 AM Mountain Time (local time)

NM Environment Department hearing officer

📍 Sunland Park Multi-Generational Center

Air permit.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Being built County approved tax-break bonds in Sept. 2025 and building has started. The state air permit for its gas fuel-cell power plant is still pending.

❓ 5 open questions about it: see below.

Last checked Nov 17, 2026.

🕒 Latest update (Nov 10, 2026): Doña Ana County commissioners voted 4-0 (one absent) to send a second breach notice to the developers. The quarterly report on local hiring, due Oct. 31 under the bond agreement, had not reached the county. Stack said it sent the numbers and had more than 5,000 workers on site in October.

What we know

  • 📍 WhereEast side of Pete V. Domenici Highway (NM 136), just south of the old railroad line, Santa Teresa, Unincorporated Doña Ana County, Doña Ana County
  • 🏢 CompanySTACK Infrastructure and BorderPlex Digital Assets (power: Yucca Growth Infrastructure)
  • 👤 Built forOracle (for OpenAI)
  • 🌳 Size1,400 acres
  • 🔌 Where the power comes fromIts own power plant (microgrid) of Bloom Energy fuel cells that run on natural gas, fed by a new gas pipeline. An earlier plan for gas turbines was dropped in April 2026.
  • 🗼 New power linesNo
  • 💧 WaterDevelopers bought water rights from a sod farm west of Sunland Park; Oracle says it will use non-potable industrial well water. A construction well approved by the State Engineer was paused by the NM Supreme Court in Aug. 2026.
  • 💵 Cost$165 billion
  • 💸 Tax breaksUp to $165 billion in county industrial revenue bonds (IRBs): no property tax for 30 years. Instead the developers pledged about $360 million in payments to the county, plus $50 million for water and sewer work.
  • 👷 Jobs promised750

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How will the gas pipeline reach the site after the State Land Office said no? 🙋 I'll find out ·
  • How much water will the campus use per day once it runs? 🙋 I'll find out ·
  • Did the county sign an agreement with the developers to keep the plans private (NDA)? 🙋 I'll find out ·
  • Will the county and the developers agree on a fix for the power plan, or will the county treat it as a breach of the bond agreement? 🙋 I'll find out ·
  • What penalty, if any, will the county set for the late hiring report? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the county's recorded bond papers: they describe the project land, including a 285-acre parcel on the east side of Pete V. Domenici Highway. We put the pin in the middle of that parcel. The 2025 satellite picture still shows desert there; work started in 2026.

    What happened so far

    • Sept 19, 2025
      Doña Ana County commissioners voted 4-1 to approve the industrial revenue bonds (up to $165 billion).
    • Jan 23, 2026
      Oracle said it is the company that will use the campus.
    • April 2026
      Developers dropped the gas turbine plan and applied instead for a gas fuel-cell power plant.
    • July 14, 2026
      The State Land Commissioner again denied a request to cross state land with a gas pipeline for the project.
    • Aug 24, 2026
      The NM Supreme Court paused the air permit hearing and the use of water from a construction well.
    • Sept 2026
      The NM Supreme Court rejected the two challenges and let the permit process go on.
    • Sept 2026
      Oracle sent the developer a force majeure notice. It lets Oracle delay rent if power problems push the campus past its planned 2028 opening. Oracle said the project is still on schedule.
    • Sept 2026
      By late September, pipeline builder Energy Transfer had moved the 17.8-mile gas pipeline route onto federal land after the State Land Office said no, and its start date moved from August to Feb. 1, 2027.
    • Oct 2026
      Oracle announced a proposed deal with El Paso Electric for backup power to the campus. It plans to pay the utility $100 million over 10 years. County commissioners said they first learned of it at their Oct. 13 meeting.
    • Oct 2, 2026
      The state Environment Secretary named retired federal judge James O. Browning as the new hearing officer for the air permit.
    • Oct 19, 2026
      Hearing officer James Browning set the air permit hearing to start Dec. 7 at 9 a.m. in Sunland Park, Source New Mexico reported. The first day is for public comment only; after that, one hour a day is set aside for public comment.
    • Oct 27, 2026
      Doña Ana County commissioners voted unanimously to tell the developers of a possible breach of the tax-break bond agreement, about the proposed power plan. County staff were told to hold talks to find a way forward.
    • Nov 10, 2026
      Doña Ana County commissioners voted 4-0 (one absent) to send a second breach notice to the developers. The quarterly report on local hiring, due Oct. 31 under the bond agreement, had not reached the county. Stack said it sent the numbers and had more than 5,000 workers on site in October.

    Local votes and rules

    ⚖️ Court case

    The New Mexico Environmental Law Center sued the County Commission for a community group and residents. It says the county approved the Project Jupiter bonds based on an incomplete application with blank pages. On March 20, 2026, a judge refused to throw out the case but also refused to pause the ordinances, so building goes on. The court will review the county's Sept. 19 and Oct. 14, 2025 actions.

    Oct 17, 2025

    ✅ Approved

    County commissioners voted 4-1 for three ordinances for Project Jupiter in Santa Teresa: tax-break bonds (industrial revenue bonds) of up to $165 billion, and two local economic development (LEDA) funding ordinances. The bond deal was made public only days before the vote, and public comment lasted over four hours. The vote is being challenged in court.

    Sept 19, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Project Jupiter · Doña Ana County · 2026
    2. Doña Ana County commissioners vote to move forward on IRB for Project Jupiter · KRWG · Sept 19, 2025
    3. Oracle Advances American AI Innovation and Local Economic Prosperity in New Mexico · Oracle · Jan 23, 2026
    4. Project Jupiter: where the AI data center project stands in NM · The Daily Lobo · Aug 17, 2026
    5. Santa Teresa's Project Jupiter touts low water use, emissions ahead of air permit hearing · KFOX14 · July 28, 2026
    6. New Mexico Supreme Court halts water use from Project Jupiter well in Santa Teresa · KFOX14 · Aug 24, 2026
    7. New Mexico land commissioner denies Project Jupiter pipeline request · KOB 4 · July 2026
    8. NM Supreme Court rejects 2 Project Jupiter challenges, allows permitting process to resume · Source NM · Sept 2026
    9. IRB Series 2025A, executed and recorded (Exhibit A-1, Description of Project Site; Instrument 2525212) · Doña Ana County · Nov 12, 2025
    10. PLSS Section 31, Township 28 South, Range 3 East · Bureau of Land Management CadNSDI · Oct 8, 2026
    11. Sentinel-2 cloudless 2025 image around the Project Jupiter parcel · EOX IT Services · 2025
    12. New hearing officer appointed in Project Jupiter permitting proceeding · Santa Fe New Mexican (via Yahoo News) · Oct 3, 2026
    13. Oracle cites force majeure over New Mexico data centre, Bloomberg reports · The Next Web · Sept 2026
    14. Oracle's New Mexico AI Data Center Faces Pipeline Delays · Hoodline · Oct 2026
    15. Data center Project Jupiter air quality permit hearing set for early December (first published by Source NM, Oct. 19) · Organ Mountain News / Source New Mexico · Oct 21, 2026
    16. Doña Ana County flags potential breach in Project Jupiter data center agreement · Albuquerque Journal · Oct 27, 2026
    17. Doña Ana County issues new breach notice to Project Jupiter developers · Albuquerque Journal · Nov 10, 2026
    18. Doña Ana County to notify Project Jupiter developers of IRB breach due to late jobs report · Searchlight New Mexico · Nov 13, 2026

    See something wrong? Tell us and we'll fix it.