Teton Digital 'Project Trinity' data center south of Tioga
Also called: Project Trinity
A planned 100 MW data center in rural Williams County, south of Tioga. The company hoped to start in late 2025, but we found no later news.
Where things stand: County let the company apply for a permit in Feb. 2025. We found no final permit or building news.
๐ Latest update (Feb 2025): Williams County commissioners allowed Teton Digital to start applying for a conditional use permit.
What we know
- ๐ Whereabout 8 miles south of Tioga, next to the Enerfore Digital site, Unincorporated Williams County, Williams County
- ๐ข CompanyTeton Digital
- โก Power it needs100 megawatts (about as much as 80,000 homes)
- โ๏ธ Coolingliquid cooling (company says it is quieter)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did Williams County grant the conditional use permit? ๐ I'll find out
- Is anything built at the site? ๐ I'll find out
- Who would use the data center? ๐ I'll find out
What happened so far
- Feb 2025Williams County commissioners allowed Teton Digital to start applying for a conditional use permit.
Local votes and rules
โ Approved
County commissioners let Teton Digital start applying for a permit for a 100 MW data center about eight miles south of Tioga. They told the company to work with nearby townships and residents, who raised noise worries. We found no final permit vote.
๐ Data center rules
Williams County added data center rules (Ordinance 2024-01-02). A data center needs a conditional use permit and must be at least 1 mile from homes, schools, churches and parks, and 3 miles from another data center. The county uses distance instead of a noise limit. In August 2024 (Ordinance 2024-08-20) it also allowed data centers in farm zones with a permit.