Proposed

Teton Digital 'Project Trinity' data center south of Tioga

Also called: Project Trinity

A planned 100 MW data center in rural Williams County, south of Tioga. The company hoped to start in late 2025, but we found no later news.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 8, 2026

Where things stand: County let the company apply for a permit in Feb. 2025. We found no final permit or building news.

๐Ÿ•’ Latest update (Feb 2025): Williams County commissioners allowed Teton Digital to start applying for a conditional use permit.

What we know

  • ๐Ÿ“ Whereabout 8 miles south of Tioga, next to the Enerfore Digital site, Unincorporated Williams County, Williams County
  • ๐Ÿข CompanyTeton Digital
  • โšก Power it needs100 megawatts (about as much as 80,000 homes)
  • โ„๏ธ Coolingliquid cooling (company says it is quieter)

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Feb 2025
    Williams County commissioners allowed Teton Digital to start applying for a conditional use permit.

Local votes and rules

โœ… Approved

County commissioners let Teton Digital start applying for a permit for a 100 MW data center about eight miles south of Tioga. They told the company to work with nearby townships and residents, who raised noise worries. We found no final permit vote.

Feb 2025

๐Ÿ“œ Data center rules

Williams County added data center rules (Ordinance 2024-01-02). A data center needs a conditional use permit and must be at least 1 mile from homes, schools, churches and parks, and 3 miles from another data center. The county uses distance instead of a noise limit. In August 2024 (Ordinance 2024-08-20) it also allowed data centers in farm zones with a permit.

Jan 2, 2024
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Williams County Commissioners give go-ahead for another data center company to apply for a conditional use permit ยท KFYR-TV ยท Feb 18, 2025

See something wrong? Tell us and we'll fix it.