Applied Digital Polaris Forge 3 AI campus near Center
Also called: Polaris Forge 3, APLD BIS-01, LLC
An AI data center campus on farmland north of Center. The county approved it 2-1 in July 2026, with rules on noise, water and roads. It would need 430 MW of power and start running in 2027.
Where things stand: County approved the permit and rezoning 2-1 on July 7, 2026. The company says it is under construction.
π Latest update (July 10, 2026): The county signed a road use agreement with the company.
What we know
- π Wherefarmland about 1 mile east of Hannover and 5 miles north of Center, near ND Highways 25 and 31, Unincorporated Oliver County, Oliver County
- π’ CompanyAPLD BIS-01, LLC (Applied Digital)
- ποΈ Owned byApplied Digital
- π€ Built forAn unnamed large tech company ("hyperscaler")
- π³ Size600 acres
- β‘ Power it needs430 megawatts (about as much as 344,000 homes)
- π Where the power comes fromMontana-Dakota Utilities, under a power deal that the state utility commission must approve.
- π§ WaterCooling water trucked in at first; no water may be put into the aquifer (county condition)
- π΅ Cost$1 billion
- π· Jobs promised200
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did the company ever post the reclamation bond the county asked for? π I'll find out
- How much water will it use each day once running, and from where? π I'll find out
- How many backup diesel generators will it have? π I'll find out
What happened so far
- March 2026Oliver County passed a 180-day pause (moratorium) on data centers.
- April 30, 2026At a special meeting, the county commission lifted the moratorium.
- May 2026Applied Digital asked the county to rezone the land from farm to industrial.
- May 20, 2026Applied Digital signed a 15-year lease with a large tech company for 300 MW at Polaris Forge 3.
- June 22, 2026Montana-Dakota Utilities signed a power deal for the 430 MW campus.
- July 7, 2026County commissioners approved the building permit 2-1, which also rezoned the land to industrial, with conditions.
- July 10, 2026The county signed a road use agreement with the company.
Local votes and rules
β Approved
Commissioners voted 2-1 to approve Applied Digital's building permit north of Center, which also rezoned the farm land to industrial. Conditions include a noise study, generator tests only from 8 a.m. to 6 p.m., cooling water brought from off site, and paying the cost of one extra sheriff's deputy.
π Other
At a special meeting, commissioners ended the county's 180-day data center pause early. A rezoning request for a data center was filed soon after.
βΈοΈ Pause on new data centers
The county paused data centers for 180 days in March 2026. (An advisory board had first suggested three years.) Commissioners ended the pause early at a special meeting on April 30, 2026.
An aerial photo of the area.
Where this comes from
- Applied Digital approved building permit for data center development Β· Central Nordak Publishing (Center Republican) Β· July 16, 2026
- Applied Digital expands in North Dakota, eyes Oliver County for third data center Β· Valley News Live Β· July 13, 2026
- Montana-Dakota Utilities Announces Electric Service Agreement with Applied Digital for Proposed AI Factory Β· MDU Resources (press release) Β· June 22, 2026
- Applied Digital submits rezoning application for data center in Oliver County Β· KFYR-TV Β· May 4, 2026
- "We are being sold down the river," Oliver County removes roadblock for data center Β· KX News Β· May 2026
- Applied Digital: $7.5 Billion Hyperscaler Lease Pushes Contracted AI Capacity Above 1 GW Β· Pulse 2.0 Β· May 25, 2026
- Applied Digital Reports Fiscal First Quarter 2027 Results Β· Applied Digital Β· Oct 7, 2026