1 data center project in Unincorporated Oliver County
Who decides here: the Oliver County Commissioners decides on zoning for land outside city and town limits.
In Unincorporated Oliver County
Local votes and rules
β Approved
Commissioners voted 2-1 to approve Applied Digital's building permit north of Center, which also rezoned the farm land to industrial. Conditions include a noise study, generator tests only from 8 a.m. to 6 p.m., cooling water brought from off site, and paying the cost of one extra sheriff's deputy.
π Other
At a special meeting, commissioners ended the county's 180-day data center pause early. A rezoning request for a data center was filed soon after.
βΈοΈ Pause on new data centers
The county paused data centers for 180 days in March 2026. (An advisory board had first suggested three years.) Commissioners ended the pause early at a special meeting on April 30, 2026.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Oliver County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Unincorporated Oliver County: Wapa-- Western Area Power Administration (public) or Montana-dakota Utilities Co. (company) or Basin Electric Power Co-op (co-op (owned by its members)) or Roughrider Electric Cooperativ (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in North Dakota.
π Open tasks here
- Did the company ever post the reclamation bond the county asked for?
- How much water will it use each day once running, and from where?
- How many backup diesel generators will it have?
- Where exactly is the site? Reports say both '1 mile east of Hannover' and 'south of Hannover near Highways 25 and 31'. A parcel number, address or agenda link helps.