πŸ“£ Report Something
Stopped or cancelled

Southeast Raleigh data center (Jones Sausage Road)

A company planned a data center of nearly 100,000 square feet on 14 acres in southeast Raleigh. More than 130 people signed up to speak against it. The request was withdrawn in August 2026.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: The buyer withdrew its request to join the city in August 2026, days before a City Council hearing.

πŸ•’ Latest update (Aug 2026): The buyer withdrew its request to annex the land into Raleigh after strong opposition.

What we know

  • πŸ“ Where14-acre site on Jones Sausage Road near Rock Quarry Road, Raleigh, Wake County
  • 🌳 Size14 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which company was behind the plan? One trade report names RadiusDC, but we could not confirm it. πŸ™‹ I'll find out

What happened so far

  • Nov 2025
    The landowner agreed to sell the parcel to a buyer.
  • Aug 2026
    The buyer withdrew its request to annex the land into Raleigh after strong opposition.

Local votes and rules

⏸️ Pause on new data centers

Raleigh paused approvals for large data centers for six months, by a 7-1 vote. The city will use the time to write rules on noise, vibration and water use. It can end sooner if new rules pass.

Oct 6, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Raleigh data center proposal withdrawn after community opposition Β· ABC11 Β· Aug 18, 2026
  2. Raleigh, Cary data center moratorium Β· WFAE Β· Sept 16, 2026

See something wrong? Tell us and we'll fix it.