Monticello Tech Park (Frattalone data center campus)
Also called: Monticello Tech, LLC, Edmonson Business Center
Monticello Tech, a Frattalone company, wants up to 3 million square feet of data centers in up to 8 buildings on about 547 acres southeast of Monticello. Its July 2026 application estimates about 75,000 gallons of water a day and building over 4 to 8 years, starting no earlier than 2028. The city is reviewing it, and an environmental group is suing over the environmental review.
What happens next?
🗓️ Public meeting: Monday, November 30, 2026, 6:30 PM Central Time (local time)
Monticello City Council meeting: this project is on the agenda
📍 Mississippi Room, Monticello Community Center, 505 Walnut Street
Special meeting.
✔ ConfirmedSourceNot live: please check with the office first.
🗓️ No meeting or deadline known yet.
Where things stand: Proposed On Nov. 9, 2026 the City Council held a public hearing and voted 3-1 to postpone action. A special council meeting on Nov. 30, 2026 will take up the annexation and the three applications. The city must decide by Dec. 8, 2026.
❓ 4 open questions about it: see below.
Last checked Nov 15, 2026.
🕒 Latest update (Nov 9, 2026): The City Council held a public hearing on the annexation request and the land use applications, then voted 3-1 to postpone action.
What we know
- 📍 WhereFarmland east of Highway 25 and south of 85th St. NE, Monticello Township (orderly annexation area), Monticello, Wright County
- 🏢 CompanyMonticello Tech, LLC (Frattalone Companies)
- 🌳 Size547 acres
- 💧 WaterCity of Monticello water and sewer, to be extended to the site · 75,000 gallons a day
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which company would use the data centers? 🙋 I'll find out ·
- How much electricity would the campus use, and who would supply it? 🙋 I'll find out ·
- What did the court decide at the fall 2026 motion hearings? 🙋 I'll find out ·
- When will the Monticello City Council vote on annexing the land and on the three applications? (The city's deadline to act is Dec. 8, 2026.) 🙋 I'll find out ·
What happened so far
- Feb 2025City approved a comprehensive plan change for the site.
- April 2025Petitions were filed to annex the land into the city.
- Feb 25, 2026Minnesota Center for Environmental Advocacy (MCEA) sued the city and Monticello Tech in Wright County court over the environmental review (AUAR).
- March 9, 2026Residents spoke against the data centers at a City Council meeting. The city said neither project is approved.
- April 27, 2026City Council voted 4-1 for a data center ordinance with new rules, which opens the door to applications.
- July 6, 2026Monticello Tech filed its land use applications (rezoning to a data center planned development, a conditional use permit and a preliminary plat). Staff later found them incomplete.
- Aug 3, 2026Monticello Tech filed a revised application. It estimates about 75,000 gallons of water a day on average and construction starting no earlier than 2028.
- Aug 24, 2026City Council approved a deal making the developer pay the city's review costs.
- Oct 6, 2026The Planning Commission voted 4-1 to recommend approval of Monticello Tech's three applications (rezoning, conditional use permit and preliminary plat) for about 547 acres, filed as 'Edmonson Business Center'.
- Oct 19, 2026Monticello Tech gave the city more supporting documents (after others on Oct. 15).
- Nov 9, 2026The City Council held a public hearing on the annexation request and the land use applications, then voted 3-1 to postpone action.
Local votes and rules
📜 Data center rules
Monticello passed rules for data centers, 4-1. A data center needs a special planned development approval. Near homes it must be 300 feet away with full screening, or 700 feet without. Developers must pay for all needed roads, pipes and power.
⚖️ Court case
The Minnesota Center for Environmental Advocacy sued Monticello and Monticello Tech over the environmental review for a data center campus of 3 to 5 million square feet.
Drag the slider to compare the land before and now.
Where this comes from
- Two data center proposals on the table in Monticello · Monticello Times · April 27, 2026
- Monticello residents rally against proposed data centers · FOX 9 · March 9, 2026
- Legal updates on MCEA's data center cases · Minnesota Center for Environmental Advocacy · May 15, 2026
- City of Monticello sets stage for allowing data centers, with restrictions · MPR News · April 28, 2026
- Monticello gets more details on proposed data center (summary of Hometown Source) · Blandin on Broadband · Aug 13, 2026
- Monticello Tech set to pay city costs for data center review (summary of Monticello Times) · Blandin on Broadband · Sept 2, 2026
- 85th Street NE (OpenStreetMap) · OpenStreetMap contributors (ODbL) · Oct 8, 2026
- What the planning commission's data center votes mean · Monticello Times · Oct 12, 2026
- Monticello Commissioners vote to recommend approval of applications that open the door to a specific hyperscale data center (Wright County) · Blandin on Broadband · Oct 13, 2026
- Monticello Tech (project page) · City of Monticello · Oct 2026