Send us a tip
Approved, not built yetBig (AI-size): 500 megawatts

Hermantown Google data center campus

Also called: Project Loon, Hermantown Data Center

Google wants to build a data center campus of up to three large buildings on about 280 acres in Hermantown, west of Duluth. It would use air cooling and new wind and battery power from Minnesota Power. Many residents oppose it, and two lawsuits challenge the city's rezoning and environmental review.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Hermantown City.

Where things stand: Approved, not built yet On Oct. 30, 2026 the City Council unanimously approved the special use permit, development deal and a $210 million plan to clean up the site if it is abandoned. State regulators must still approve the power deal with Minnesota Power. Three lawsuits are pending.

  • Nov 1, 2026: Our records now list Hermantown Google data center campus as approved Source
  • Oct 30, 2026: Hermantown, St. Louis County: project approved Source

❓ 6 open questions about it: see below.

Last checked Nov 1, 2026.

🕒 Latest update (Oct 30, 2026): City Council voted unanimously to approve a special use permit, a development agreement and a $210 million decommissioning (site clean-up) agreement. Google also agreed to check private wells near the site.

What we know

  • 📍 WhereAbout 280 acres near Midway Road and Morris Thomas Road, next to Minnesota Power's Arrowhead substation, in southwest Hermantown, Hermantown, St. Louis County
  • 🏢 CompanyGoogle (site work by Mortenson Development)
  • 🏛️ Owned byAlphabet
  • 👤 Built forGoogle
  • 🌳 Size280 acres
  • ⚡ Power it needs500 megawatts (about as much as 400,000 homes)
  • 🔌 Where the power comes fromMinnesota Power will add 700 MW of new clean energy for the project: 300 MW of wind and 400 MW of batteries.
  • 💧 Water50,000 gallons a day
  • ❄️ CoolingAir cooling (Google says almost no water for cooling)
  • 💵 Cost$2 billion
  • 💸 Tax breaksNone. Google dropped its request for a property tax break (up to $80 million) in October 2026. The city expects about $3 million a year in property taxes from the project.
  • 🤐 Privacy agreement (NDA)Yes. Several city and county officials signed agreements with the developer to keep plans private (NDAs). Three of seven St. Louis County commissioners signed one.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is Minnesota Power's planned 67-mile power line from Grand Rapids to Hermantown needed for this data center? 🙋 I'll find out ·
  • What did the agreements to keep plans private (NDAs) signed by city and county officials cover? 🙋 I'll find out ·
  • How many permanent jobs will the data center create? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
  • When will the Minnesota Public Utilities Commission decide on Google's electric service agreement with Minnesota Power? 🙋 I'll find out ·
  • What will the courts decide in the three pending lawsuits? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Jan 2025
      City signed a deal for Mortenson Development to pay $225,000 for the city's planning costs.
    • Oct 2025
      City Council voted 4-0 to rezone the land for the project and adopted a first environmental review (AUAR).
    • Nov 2025
      Developer pulled its permits from city agendas; plans were paused.
    • March 3, 2026
      Google was announced as the company behind the project, with 700 MW of new wind and battery power from Minnesota Power.
    • March 21, 2026
      City opened a 30-day comment period on a new environmental review plan (scoping), for about 278 acres.
    • April 29, 2026
      Residents' group Stop the Hermantown Data Center sued the city in St. Louis County court over the rezoning and closed meetings.
    • May 4, 2026
      City Council tabled the vote on an $80 million tax break and development deal with Google.
    • June 12, 2026
      City opened a second comment period on the draft environmental review (AUAR) and mitigation plan.
    • July 6, 2026
      City Council approved $200,000 more from Mortenson Development for planning costs.
    • Aug 2026
      Google scaled back to three buildings (1.66 million sq ft, down from four buildings and 1.8 million sq ft).
    • Oct 5, 2026
      City Council voted unanimously to approve the final environmental review (AUAR).
    • Oct 14, 2026
      City staff said Google will no longer ask for a property tax break for the data center.
    • Oct 30, 2026
      City Council voted unanimously to approve a special use permit, a development agreement and a $210 million decommissioning (site clean-up) agreement. Google also agreed to check private wells near the site.

    Local votes and rules

    ✅ Approved

    The City Council voted unanimously to approve a special use permit, a development agreement and a $210 million site clean-up (decommissioning) agreement for Google's data center. Google had dropped its tax break request. Three lawsuits against the project are still pending.

    Oct 30, 2026

    ✅ Approved

    Hermantown's council unanimously approved the final environmental review (AUAR) for the proposed Google data center. A $80 million tax break and a development deal still need votes.

    Oct 5, 2026

    🤝 Agreement with the company

    Hermantown's council approved deals for Mortenson Development to pay $200,000 more for city planning costs, and for Minnesota Power to pay $20,000 for a review of a power line to the data center site.

    July 6, 2026

    ⚖️ Court case

    The residents' group Stop the Hermantown Data Center sued the city over the rezoning for Google's data center. It says the city spot-zoned the land and held three closed meetings that broke the open meeting law.

    April 29, 2026

    ⚖️ Court case

    The Minnesota Center for Environmental Advocacy and the group Stop the Hermantown Data Center sued over the city's environmental review. They want a fuller review and no permits until it is done. The case is on hold while the city redoes its review.

    Nov 5, 2025

    🗺️ Zoning change

    Hermantown's council voted 4-0 to rezone more than 200 acres for a large data center, even though residents asked for a pause. The company behind it was later named as Google.

    Oct 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Google behind proposed Hermantown data center · Northern News Now · March 3, 2026
    2. At packed Hermantown open house, Google tries to ease data center concerns · MPR News · June 25, 2026
    3. More details emerge as Google, Hermantown work out data center agreements · KAXE · May 20, 2026
    4. Citizens' group files lawsuit to block Google's proposed Hermantown data center · MPR News · April 29, 2026
    5. Opponents of data centers join with critics of power line proposal in northern Minnesota · MPR News · April 8, 2026
    6. Controversial AI data center proposal near Lake Superior's shore · North Shore Journal · Oct 29, 2025
    7. Hermantown City Council approves data center reimbursements · Northern News Now · July 7, 2026
    8. Public comments open on updated review of proposed Hermantown data center · KAXE · March 31, 2026
    9. Hermantown opens second public comment period for proposed Google data center · Northern News Now · June 12, 2026
    10. Data center developer pulls permits from Hermantown agendas · KAXE · Nov 17, 2025
    11. Google has scaled back its plans for a proposed data center in Hermantown (summary of Star Tribune) · Blandin on Broadband · Aug 21, 2026
    12. Hermantown council unanimously passes AUAR review for proposed data center · Northern News Now · Oct 6, 2026
    13. Google drops request for tax relief for Hermantown data center proposal · KAXE · Oct 15, 2026
    14. Hermantown approves controversial Google data center during late night meeting · MPR News · Oct 31, 2026

    See something wrong? Tell us and we'll fix it.