1 data center project in Hermantown City
Who decides here: the City Council of Hermantown City votes on zoning. The St. Louis County may review big projects too.
In Hermantown City
Local votes and rules
β Approved
Hermantown's council unanimously approved the final environmental review (AUAR) for the proposed Google data center. A $80 million tax break and a development deal still need votes.
π€ Agreement with the company
Hermantown's council approved deals for Mortenson Development to pay $200,000 more for city planning costs, and for Minnesota Power to pay $20,000 for a review of a power line to the data center site.
βοΈ Court case
The residents' group Stop the Hermantown Data Center sued the city over the rezoning for Google's data center. It says the city spot-zoned the land and held three closed meetings that broke the open meeting law.
βοΈ Court case
The Minnesota Center for Environmental Advocacy and the group Stop the Hermantown Data Center sued over the city's environmental review. They want a fuller review and no permits until it is done. The case is on hold while the city redoes its review.
πΊοΈ Zoning change
Hermantown's council voted 4-0 to rezone more than 200 acres for a large data center, even though residents asked for a pause. The company behind it was later named as Google.
What you can do
- Get told first.
We'll email you if anything changes in Hermantown City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Allete, Inc. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Minnesota.
π Open tasks here
- Will the City Council approve the $80 million tax break and development deal, and when?
- How much electricity (megawatts) will the data center use?
- Is Minnesota Power's planned 67-mile power line from Grand Rapids to Hermantown needed for this data center?
- What did the secret deals (NDAs) signed by city and county officials cover?
- How many permanent jobs will the data center create?