1 data center project in Hermantown City
Who decides here: the City Council of Hermantown City votes on zoning. The St. Louis County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Local votes and rules
✅ Approved
The City Council voted unanimously to approve a special use permit, a development agreement and a $210 million site clean-up (decommissioning) agreement for Google's data center. Google had dropped its tax break request. Three lawsuits against the project are still pending.
✅ Approved
Hermantown's council unanimously approved the final environmental review (AUAR) for the proposed Google data center. A $80 million tax break and a development deal still need votes.
🤝 Agreement with the company
Hermantown's council approved deals for Mortenson Development to pay $200,000 more for city planning costs, and for Minnesota Power to pay $20,000 for a review of a power line to the data center site.
⚖️ Court case
The residents' group Stop the Hermantown Data Center sued the city over the rezoning for Google's data center. It says the city spot-zoned the land and held three closed meetings that broke the open meeting law.
⚖️ Court case
The Minnesota Center for Environmental Advocacy and the group Stop the Hermantown Data Center sued over the city's environmental review. They want a fuller review and no permits until it is done. The case is on hold while the city redoes its review.
🗺️ Zoning change
Hermantown's council voted 4-0 to rezone more than 200 acres for a large data center, even though residents asked for a pause. The company behind it was later named as Google.
What you can do
- Get told first.
We'll email you if anything changes in Hermantown City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Allete, Inc. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Minnesota.
🙋 Open tasks here
- Is Minnesota Power's planned 67-mile power line from Grand Rapids to Hermantown needed for this data center?
- What did the agreements to keep plans private (NDAs) signed by city and county officials cover?
- How many permanent jobs will the data center create?
- Where exactly is the site? A parcel number, address or agenda link helps.
- When will the Minnesota Public Utilities Commission decide on Google's electric service agreement with Minnesota Power?
- What will the courts decide in the three pending lawsuits?