Approved, not built yet

Cannon Falls Technology Park (Tract data center campus)

Tract plans a 1.75 million square foot data center campus on about 253 acres at the edge of Cannon Falls. The city approved it in November 2025. Tract says it will take up to 10 years to build and create about 275 long-term jobs. No company that will use it has been named.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City Council approved the permit and development deal 4-2 in November 2025.

๐Ÿ•’ Latest update (Nov 2025): City Council approved the conditional use permit and development agreement, 4-2, and rezoned the land to industrial.

What we know

  • ๐Ÿ“ WhereBetween Rochester Boulevard and Highway 52, on land annexed from Randolph Township, Cannon Falls, Dakota County
  • ๐Ÿข CompanyTract
  • ๐ŸŒณ Size253 acres
  • ๐Ÿ”Œ Where the power comes fromDakota Electric Association, not Xcel Energy. Tract will build a new substation. The permit covers overhead power lines.
  • ๐Ÿ—ผ New power linesYes
  • ๐Ÿ’ง WaterCity of Cannon Falls
  • ๐Ÿ‘ท Jobs promised275

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Aug 2025
    Cannon Falls annexed about 240 acres from Randolph Township for the project.
  • Sept 8, 2025
    Planning Commission took up the rezoning, permit and plat.
  • Nov 2025
    City Council approved the conditional use permit and development agreement, 4-2, and rezoned the land to industrial.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Cannon Falls explores major data center project following land annexation ยท KTTC ยท Aug 26, 2025
  2. Cannon Falls moving toward approvals on data center project ยท Post Bulletin ยท Aug 31, 2025
  3. Cannon Falls City Council approves permits for data center project ยท Post Bulletin ยท Nov 6, 2025

See something wrong? Tell us and we'll fix it.