Being builtBig (AI-size): 2,100 megawatts

Heartland Industrial Park AI data center (Fluidstack, near Merom)

Also called: Next Frontier Indiana Campus, Heartland Industrial Park, Fluidstack Sullivan County

Fluidstack and partners are building a large AI data center campus next to the Merom coal plant in Sullivan County. The first phase is two buildings (430 MW) on about 140 acres; the full site could reach 2.1 gigawatts on about 1,000 acres. The company promised $50 million to the county and says it uses closed-loop cooling.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Where things stand: Being built Phase 1 is under construction. The first data hall is planned to open in July 2027.

❓ 5 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 6, 2026): Fluidstack held a public open house in Merom about the project.

What we know

  • 📍 WhereHeartland Industrial Park, between County Road 400 West and the Merom Generating Station, outside New Lebanon, Sullivan County
  • 🏢 CompanyMeridian Arc HoldCo (Fluidstack and a Coatue-affiliated company); site developer Potentia
  • 🏛️ Owned byFluidstack
  • 👤 Built forunknown (Google backs the lease)
  • 🌳 Size1,000 acres
  • ⚡ Power it needs2,100 megawatts (about as much as 1,680,000 homes)
  • 🔌 Where the power comes fromPower through Hoosier Energy and WIN Energy REMC, next to Hallador's coal-fired Merom Generating Station. The developer says it pays all energy costs.
  • ❄️ CoolingClosed-loop cooling: filled once, then reused
  • 💵 Cost$65 billion
  • 💸 Tax breaksThe developer says it asked for no property tax breaks for Phase 1.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many diesel backup generators will the campus have? 🙋 I'll find out ·
  • Will new power lines be built, and who pays for them? 🙋 I'll find out ·
  • Who is the end user of the computing power? 🙋 I'll find out ·
  • Is the $50 million county agreement signed, and is it public? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the pin is on County Road 100 South between County Road 400 West and the Merom power plant, as described for the Heartland Industrial Park.

    What happened so far

    • 2026
      A $5.7 billion financing deal closed for the first 430 MW phase on about 140 acres, with Google backing the lease.
    • Aug 6, 2026
      Fluidstack held a public open house in Merom about the project.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. FluidStack hosts open house for Sullivan County data center campus · WTHI-TV · Aug 6, 2026
    2. Sullivan County data center (project website) · Fluidstack
    3. Data center start-up Potentia behind 2.1 GW Indiana project now backed by Fluidstack and Google · New Project Media · 2026
    4. OpenStreetMap: Merom Power Station outline · OpenStreetMap contributors · Oct 8, 2026
    5. OpenStreetMap: West County Road 100 South, Sullivan County · OpenStreetMap contributors · Oct 8, 2026
    6. Fluidstack Sullivan County (listed on W County Rd 100 S, Merom) · Data Center Map · Oct 8, 2026