Send us a tip
Approved, not built yetBig (AI-size): 400 megawatts

Pittsboro data center campus (Raeden; first planned by Vantage)

Also called: Vantage IN11, Hendricks County Technology Campus

Vantage Data Centers plans a campus on about 285 acres of a 626-acre farm site in Pittsboro. The plan shows three buildings of 256, 96 and 48 megawatts (about 400 MW in all). The town rezoned the land in March 2025.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Council of Pittsboro Town.

Where things stand: Approved, not built yet Raeden plans a data center campus on the about 625-acre site (rezoned for Vantage in 2025). The town zoning appeals board approved an on-site gas power plant 3-2 on Nov. 12, 2026. A state air permit is still needed.

❓ 8 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 12, 2026): The Pittsboro Board of Zoning Appeals voted 3-2 to approve, with conditions, a special exception for a natural gas power plant on about 265 acres to power the data center.

What we know

  • 📍 WhereBetween County Roads 850 North and 1000 North, west of County Road 500 East, north of I-74, Pittsboro, Hendricks County
  • 🏢 CompanyRaeden (Raeden Acquisitions, LLC)
  • 👤 Built forunknown (shared by several tenants)
  • 🌳 Size626 acres
  • ⚡ Power it needs400 megawatts (about as much as 320,000 homes)
  • 🔌 Where the power comes fromA natural gas power plant on about 264 acres of the site (36 gas engines, 200-300 MW at first), later power through Hendricks Power Cooperative and Wabash Valley Power Alliance.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will it use per day? 🙋 I'll find out ·
  • Were any tax breaks given? 🙋 I'll find out ·
  • How will the buildings be cooled, and how many jobs are promised? 🙋 I'll find out ·
  • What did the court decide in the residents' lawsuit? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
  • Is Vantage still involved in any way, now that Raeden plans the campus? 🙋 I'll find out ·
  • Has IDEM received or approved an air permit for the gas power plant? 🙋 I'll find out ·
  • What conditions and commitments did the zoning appeals board attach to the power plant approval? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the site is described as bounded by County Roads 500 East, 850 North and 1000 North. The pin is placed by hand inside those roads.

    What happened so far

    • Feb 25, 2025
      Pittsboro Advisory Plan Commission voted 4-1 to recommend rezoning the land to warehouse industrial.
    • March 2025
      Pittsboro Town Council approved the rezoning unanimously.
    • April 2025
      Residents sued in Hendricks Circuit Court, saying notice was not enough and no traffic, water or environmental studies were required.
    • July 2025
      Vantage Data Centers withdrew from the Pittsboro site.
    • Nov 12, 2026
      The Pittsboro Board of Zoning Appeals voted 3-2 to approve, with conditions, a special exception for a natural gas power plant on about 265 acres to power the data center.

    Local votes and rules

    ⚖️ Court case

    Residents sued the town, its council and plan commission, and Vantage. They say the town did not give enough notice of the annexation and rezoning and did not require traffic, environmental or water studies.

    April 2025

    ✅ Approved

    The town council voted 5-0 to rezone about 626 acres of farmland to industrial for a Vantage Data Centers campus.

    March 18, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data center developer eyeing 618-acre site in Hendricks County · Inside Indiana Business · Feb 2025
    2. Pittsboro officials OK rezoning of 626 acre-site for proposed data center campus · Inside Indiana Business · March 2025
    3. Pittsboro residents ask court to halt planned Hendricks County data center · Inside Indiana Business · 2025
    4. Vantage Pittsboro campus (within County Roads 500 E, 850 N and 1000 N) · Data Center Map · Oct 8, 2026
    5. OpenStreetMap: East County Road 850 North at North County Road 500 East · OpenStreetMap contributors · Oct 8, 2026
    6. Data Center for Pittsboro? Raeden hopes so. · The Republican (Hendricks County) · Nov 4, 2026
    7. 2026-BZA-02 amended staff report: special exception for power plant · Town of Pittsboro Board of Zoning Appeals · Nov 9, 2026
    8. Town of Pittsboro Board of Zoning Appeals approves special exception for data center power plant · FOX59 · Nov 13, 2026