Send us a tip
Stopped or cancelledBig (AI-size): 550 acres

Prologis data center proposal near Leesburg

Prologis asked to rezone about 550 acres of farmland near Leesburg for a data center. The plan commission and county commissioners both said no in April 2025, and Prologis dropped the plan.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled County commissioners denied the rezoning in April 2025.

❓ 1 open question about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (April 22, 2025): County commissioners voted unanimously against the rezoning.

What we know

  • 📍 WhereFarmland near Leesburg, Kosciusko County
  • 🏢 CompanyPrologis
  • 🌳 Size550 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked for the exact site location but found no address, parcel or precise road description.

    What happened so far

    • April 2025
      Kosciusko County Plan Commission rejected rezoning the farmland.
    • April 22, 2025
      County commissioners voted unanimously against the rezoning.

    Local votes and rules

    ✋ Turned down

    County commissioners voted unanimously against rezoning about 550 acres of farmland west of Leesburg for a Prologis data center. Prologis said it would not pursue the project.

    April 22, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something