Prologis data center proposal near Leesburg
Prologis asked to rezone about 550 acres of farmland near Leesburg for a data center. The plan commission and county commissioners both said no in April 2025, and Prologis dropped the plan.
What happens next?
Where things stand: Stopped or cancelled County commissioners denied the rezoning in April 2025.
❓ 1 open question about it: see below.
📣 See work going on anyway? Tell us
Last checked Oct 8, 2026.
🕒 Latest update (April 22, 2025): County commissioners voted unanimously against the rezoning.
What we know
- 📍 WhereFarmland near Leesburg, Kosciusko County
- 🏢 CompanyPrologis
- 🌳 Size550 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked for the exact site location but found no address, parcel or precise road description.
What happened so far
- April 2025Kosciusko County Plan Commission rejected rezoning the farmland.
- April 22, 2025County commissioners voted unanimously against the rezoning.
Local votes and rules
✋ Turned down
County commissioners voted unanimously against rezoning about 550 acres of farmland west of Leesburg for a Prologis data center. Prologis said it would not pursue the project.
Drag the slider to compare the land before and now.
Where this comes from
- Kosciusko County Commissioners vote against rezoning for proposed Leesburg data center · 21Alive · April 22, 2025
- Kosciusko County plan commission rejects rezoning farmland for proposed data center · WNDU · April 2, 2025
See something wrong? Tell us and we'll fix it.