Prologis data center proposal near Leesburg
Prologis asked to rezone about 550 acres of farmland near Leesburg for a data center. The plan commission and county commissioners both said no in April 2025, and Prologis dropped the plan.
Where things stand: County commissioners denied the rezoning in April 2025.
🕒 Latest update (April 22, 2025): County commissioners voted unanimously against the rezoning.
What we know
- 📍 WhereFarmland near Leesburg, Kosciusko County
- 🏢 CompanyPrologis
- 🌳 Size550 acres
What happened so far
- April 2025Kosciusko County Plan Commission rejected rezoning the farmland.
- April 22, 2025County commissioners voted unanimously against the rezoning.
Local votes and rules
✋ Turned down
County commissioners voted unanimously against rezoning about 550 acres of farmland west of Leesburg for a Prologis data center. Prologis said it would not pursue the project.
April 22, 2025
🛰️ See it from above
An aerial photo of the area.
Photos: USGS The National Map.
Where this comes from
- Kosciusko County Commissioners vote against rezoning for proposed Leesburg data center · 21Alive · April 22, 2025
- Kosciusko County plan commission rejects rezoning farmland for proposed data center · WNDU · April 2, 2025