USA โ€บ Indiana โ€บ Clark County โ€บ Jeffersonville City
Being built

Meta Jeffersonville data center (River Ridge)

Also called: Meta Jeffersonville Data Center

Meta is building a 700,000 square foot data center on a 619-acre site at the River Ridge Commerce Center in Jeffersonville. It costs about $800 million and Meta promised 100 permanent jobs. Meta said it would open in 2026.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Under construction since January 2024. Meta said it should open in 2026; in July 2026 it was reported as nearing completion.

๐Ÿ•’ Latest update (July 2026): Local public radio reported the building was nearing completion.

What we know

  • ๐Ÿ“ WhereRiver Ridge Commerce Center, Jeffersonville, Jeffersonville, Clark County
  • ๐Ÿข CompanyMeta Platforms
  • ๐Ÿ›๏ธ Owned byMeta Platforms
  • ๐Ÿ‘ค Built forMeta
  • ๐ŸŒณ Size619 acres
  • ๐Ÿ”Œ Where the power comes fromMeta says the site will be matched with 100% renewable energy.
  • ๐Ÿ’ต Cost$800 million
  • ๐Ÿ’ธ Tax breaksThe state offered a 35-year sales tax exemption on data center equipment and energy purchases, with extra years for more investment.
  • ๐Ÿ‘ท Jobs promised100

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Jan 2024
    Meta and the governor announced an $800 million, 700,000 sq ft data center at River Ridge. Construction started that month.
  • July 2026
    Local public radio reported the building was nearing completion.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Meta to build $800M data center, add 100 jobs at River Ridge ยท Inside Indiana Business ยท Jan 25, 2024
  2. Gov. Holcomb announces Meta to build an $800M Data Center Campus in Indiana ยท River Ridge Commerce Center ยท Jan 25, 2024
  3. Southern Indiana municipalities moving quickly to address data center zoning ยท Louisville Public Media ยท July 9, 2026

See something wrong? Tell us and we'll fix it.