Being builtBig (AI-size): 304 acres

Amazon (AWS) Jasper County data center (Project Rise)

Also called: Project Rise

Amazon plans a $7 billion data center campus with up to nine buildings on 304 acres near the Schahfer power plant. County commissioners approved the deal in June 2026. Amazon will also pay $25 million to bring public water to more of Wheatfield Township.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Jasper County Board of Commissioners (for Wheatfield Township).

Where things stand: Being built Amazon held a groundbreaking on Nov. 12, 2026; Ryan Companies is the general contractor.

  • Nov 16, 2026: Our records now list Amazon (AWS) Jasper County data center (Project Rise) as being built Source

❓ 4 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 12, 2026): Amazon held a groundbreaking for the $7 billion, 304-acre campus. More than 350 workers were already on site.

What we know

  • 📍 Where2778-2938 County Road 1350 North, east of the Schahfer power plant, Wheatfield area, Wheatfield Township, Jasper County
  • 🏢 CompanyAmazon Web Services
  • 🏛️ Owned byAmazon
  • 👤 Built forAmazon Web Services
  • 🌳 Size304 acres
  • 🔌 Where the power comes fromNIPSCO; the site is next to the R.M. Schahfer Generating Station.
  • ❄️ CoolingMostly air cooling; water cooling about 2% of the year (company claim)
  • 💵 Cost$7 billion
  • 💸 Tax breaksAmazon pays $98 million up front plus $23 million a year for 10 years to the county.
  • 👷 Jobs promised250

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will the Jasper County campus use? 🙋 I'll find out ·
  • How much water will it use per day? 🙋 I'll find out ·
  • How many diesel generators are planned? 🙋 I'll find out ·
  • Is the site in Wheatfield Township or a neighboring township? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the air permit address range is on County Road 1350 North, just east of the Schahfer power plant.

    What happened so far

    • June 17, 2026
      Jasper County commissioners unanimously approved development agreements for the $7 billion campus.
    • Nov 12, 2026
      Amazon held a groundbreaking for the $7 billion, 304-acre campus. More than 350 workers were already on site.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Jasper County approves Amazon Web Services $7B data center project · Inside Indiana Business · June 19, 2026
    2. Officials approve Jasper County Amazon data center · Northwest Indiana Business Magazine · June 2026
    3. IDEM notice: Amazon Data Services, Inc., 2938-2778 County Rd 1350 N, Wheatfield, draft air permit T 073-50413-00077 · Indiana Department of Environmental Management · Sept 2026
    4. IndianaMap parcels on E 1350 N, Wheatfield (2837 E 1350 N at 41.2065, -86.9909) · Indiana Geographic Information Office (IndianaMap) · Oct 8, 2026
    5. Amazon breaks ground on $7B Wheatfield data center campus · Inside INdiana Business · Nov 13, 2026
    6. AWS breaks ground on $7bn data center in Indiana · Data Center Dynamics · Nov 16, 2026

    See something wrong? Tell us and we'll fix it.