Send us a tip
Approved, not built yet

QLEVR data center, Shadow Lake Business Park (Charlestown)

Also called: Charlestown data center

A Florida company, QLEVR, wants to build one small 3-megawatt data center (about 55,000 sq ft) on about 12 acres in Charlestown. It would cost about $105 million and bring up to 20 jobs. The plan commission approved it 4-3 with conditions after many neighbors spoke against it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Charlestown City.

Where things stand: Approved, not built yet The plan commission approved it 4-3 in July 2026 with conditions. More approvals and an environmental study are still needed.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (July 2026): The Charlestown Advisory Plan Commission voted 4-3 to let it move forward, with conditions: an environmental study, a berm with trees, blast surveys, one building only, and proof it will not strain city power or water.

What we know

  • 📍 Where1800 Cristiani Parkway, Shadow Lake Business Park, Charlestown, Clark County
  • 🏢 CompanyQLEVR LLC
  • 🌳 Size12 acres
  • ⚡ Power it needs3 megawatts (about as much as 2,400 homes)
  • 💵 Cost$105 million
  • 👷 Jobs promised20

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has the environmental study been done, and is it public? 🙋 I'll find out ·
  • How much water will it use, and will the cooling water be tested before it goes to the city sewer plant as required? 🙋 I'll find out ·
  • How many diesel generators will it have? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: 1800 Cristiani Parkway is not in any address map yet (the road opened in 2025). The pin is by hand on the side of Cristiani Parkway across from the homes on Woodford Drive.

    What happened so far

    • May 2026
      QLEVR LLC proposed a 55,000 sq ft data center in the Shadow Lake Business Park.
    • July 2026
      The Charlestown Advisory Plan Commission voted 4-3 to let it move forward, with conditions: an environmental study, a berm with trees, blast surveys, one building only, and proof it will not strain city power or water.

    Local votes and rules

    ⏸️ Pause on new data centers

    The Common Council voted unanimously for a one-year pause on new data centers and battery storage sites while the city updates its land use rules. It came after the plan commission approved the QLEVR data center in July.

    Aug 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Charlestown approves $105 million data center despite heavy opposition · Inside Indiana Business · July 22, 2026
    2. Charlestown board pushes $105 million data center ahead as neighbors fume · Hoodline · July 2026
    3. OpenStreetMap: Cristiani Pkwy, Charlestown · OpenStreetMap contributors · Oct 8, 2026
    4. QLevr Charlestown (site across from homes on Woodford Drive) · Baxtel · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.