ProposedBig (AI-size): 420 acres

Karis possible data center east of Dubuque Regional Airport

Florida real estate firm Karis contacted Dubuque County and the City of Dubuque about a possible data center east of the regional airport. No application has been filed. The county has paused data centers for 12 months.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Where things stand: Proposed Only early contact; no application. Dubuque County has a 12-month moratorium.

❓ 3 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (May 26, 2026): Dubuque County supervisors passed a 12-month data center moratorium.

What we know

  • 📍 WhereLand east of Dubuque Regional Airport, unknown, Dubuque County
  • 🏢 CompanyKaris (Karis Critical)
  • 🌳 Size420 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the land inside Dubuque city limits or in the county? 🙋 I'll find out ·
  • How many acres and how much power would it need? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • May 2026
      Karis contacted Dubuque County about a possible project.
    • May 26, 2026
      Dubuque County supervisors passed a 12-month data center moratorium.

    Local votes and rules

    ⏸️ Pause on new data centers

    Dubuque's council planned to vote September 8 on a six-month pause on data centers, with a full ordinance to follow by December. In a city survey, 76% of 3,777 people said they would not support a data center. No data center has applied inside the city.

    Sept 8, 2026

    ⏸️ Pause on new data centers

    Supervisors voted 2-1 to pause data centers for 12 months. The first plan was 4 months; it was made longer at the meeting. County staff will write zoning rules and hold town halls. The county zoning board had asked for the pause. Later the county set aside the idea of a full ban and is writing an ordinance instead.

    May 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Real estate company looking at Dubuque County land for possible data center · KCRG · June 26, 2026
    2. Developers scouting multiple data center sites in Dubuque County · Telegraph Herald · Aug 22, 2026

    See something wrong? Tell us and we'll fix it.