Possible data center site in Metter (off East Hiawatha Street)

A group representing landowners has talked with local leaders about a data center on land inside Metter, off East Hiawatha Street. No plans or size have been shared and no application has been filed.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Metter City.

Where things stand: Proposed A group representing landowners approached the city in September 2026. No application had been filed. Metter City Council set up a data center task force.

❓ 3 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Sept 15, 2026): Local leaders said a second group had approached about a data center inside Metter city limits. Metter City Council created a data center task force.

What we know

  • 📍 WhereInside Metter city limits, west of Highway 129 off East Hiawatha Street, Metter, Candler County

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is behind this proposal, and has an application been filed with the City of Metter? 🙋 I'll find out ·
  • How big would it be (acres, buildings, megawatts)? 🙋 I'll find out ·
  • What will the Metter data center task force recommend? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 15, 2026
      Local leaders said a second group had approached about a data center inside Metter city limits. Metter City Council created a data center task force.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Two groups propose data centers in Metter, Candler County · WTOC · Sept 15, 2026

    See something wrong? Tell us and we'll fix it.