USA โ€บ Georgia โ€บ Jackson County โ€บ Maysville Town
Being built

Northern Data / Rumble data center (Maysville)

A data center linked to Northern Data and Rumble is moving ahead in Maysville. In August 2026 the state approved its land disturbance plan for clearing and grading. Residents have packed meetings over water, noise, power and property values.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 6, 2026

Where things stand: State approved the land disturbance plan in Aug. 2026; only clearing and grading are allowed so far.

๐Ÿ•’ Latest update (Aug 3, 2026): City inspector reported the state and the Georgia Soil and Water Conservation Commission approved clearing and grading; the meeting ended early amid crowd anger.

What we know

  • ๐Ÿ“ WhereMaysville (the city lies in both Banks and Jackson counties), Maysville, Jackson County
  • ๐Ÿข CompanyNorthern Data / Rumble (as named by residents and the paper)

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Aug 3, 2026
    City inspector reported the state and the Georgia Soil and Water Conservation Commission approved clearing and grading; the meeting ended early amid crowd anger.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Data center to proceed with land use disturbance following state approval ยท MainStreet News (Banks County News) ยท Aug 3, 2026

See something wrong? Tell us and we'll fix it.