Approved, not built yetBig (AI-size): 3,210 megawatts

OpenAI data center campus near Rincon (Savannah Gateway Industrial Hub)

Also called: Project Camellia, Project Gateway, Octans Georgia

OpenAI plans a $20 billion AI data center on about 1,400 acres near Rincon. It would use 3.2 gigawatts of power from Georgia Power, more than any other customer in the state. The deal was made in secret. Three lawsuits now challenge it: one over the zoning, one over the development authority's vote, and one asking for money damages.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Tuesday, November 17, 2026, 5:00 PM Eastern Time (local time)

Effingham County Board of Commissioners meeting

📍 Effingham County complex, Springfield

The Savannah Morning News says commissioners are expected to vote on the site plan and that a data center moratorium is on the agenda. We did not open the official agenda, so we could not confirm the site plan is listed.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Approved, not built yet On Nov. 3, 2026, county commissioners voted unanimously to put off the site plan vote until Nov. 17. They want written promises on an earthen berm and answers on wetlands. A third lawsuit was filed Nov. 6.

❓ 8 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 6, 2026): Three residents sued OpenAI, its affiliate Octans GA LLC, the county development authority, the county commissioners and others in Effingham County State Court. They claim fraud, hiding facts and a state RICO violation, and ask for money damages.

What we know

  • 📍 WhereSavannah Gateway Industrial Hub near Rincon, south of GA 119; less than 1 mile from Blandford Elementary School, Unincorporated Effingham County, Effingham County
  • 🏢 CompanyOctans Georgia LLC (OpenAI's local company)
  • 🏛️ Owned byOpenAI
  • 👤 Built forOpenAI
  • 🌳 Size1,440 acres
  • ⚡ Power it needs3,210 megawatts (about as much as 2,568,000 homes)
  • 🔌 Where the power comes fromGeorgia Power will supply about 3.2 gigawatts (3,210 MW in the state filing) in phases from 2028 to 2032 under a 25-year contract. That is about as much power as 2 million homes.
  • 💧 WaterEffingham County water plant, per the state filing. New wells into the Floridan aquifer are not allowed in this 'red zone'; the county is building a Savannah River water plant. · 30,000 gallons a day
  • ❄️ CoolingClosed-loop dry cooling (heat sent to outdoor air, like a car radiator); no evaporative cooling towers planned, per OpenAI
  • 💵 Cost$20 billion
  • 💸 Tax breaks50% property tax cut for 15 years from the Effingham County Industrial Development Authority. County leaders still expect about $870 million in property taxes over 15 years. OpenAI also promised an $80 million community fund.
  • 👷 Jobs promised400

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will the cooling system need for its first fill and each year after, and where will it come from? 🙋 I'll find out ·
  • Will new power plants or high-voltage power lines be built to serve it, and who pays? 🙋 I'll find out ·
  • Did any official sign an agreement to keep the plans private (NDA) during the talks? 🙋 I'll find out ·
  • How many diesel backup generators will the site have? 🙋 I'll find out ·
  • Will the Army Corps hold a public hearing on the wetlands permit, and when will it decide? 🙋 I'll find out ·
  • How many data center buildings are in the final plan? The Army Corps notice shows four; a news report on the county site plan says six. 🙋 I'll find out ·
  • What will Effingham County commissioners decide on the site plan on Nov. 17, 2026? 🙋 I'll find out ·
  • Will the developer put the 20-foot earthen berm along Hodgeville Road in writing? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 2026
      Effingham County Industrial Development Authority voted on the deal with OpenAI's company Octans Georgia, including a 50% property tax break.
    • July 22, 2026
      OpenAI and county leaders announced the $20 billion, 3.2 gigawatt data center. The county filed a state regional impact review (DRI) the same day.
    • Aug 27, 2026
      Georgia Public Service Commission staff approved Georgia Power's contract to serve the data center, with added protections for other customers.
    • Sept 1, 2026
      The regional commission finished its state regional impact review (DRI) finding.
    • Sept 3, 2026
      Three residents sued the county, saying it skipped a required public hearing before allowing data centers in the industrial zone.
    • Sept 14, 2026
      The county pulled the site plan review from the Sept. 15 commission agenda to allow more review time.
    • Sept 21, 2026
      Five residents and the group One Hundred Miles sued the development authority over secrecy and asked a judge to throw out its deals with Octans Georgia.
    • Oct 5, 2026
      The U.S. Army Corps of Engineers published a public notice for Octans GA, LLC's permit to fill about 72 acres of wetland and 1.5 acres of ditch on the 1,336-acre site. About 22 acres of that were already allowed by an older industrial park permit. The plan shows four data center buildings, each with cooling, battery storage and a power substation.
    • Oct 21, 2026
      Effingham County commissioners unanimously hired Charles Abbott Associates to handle plan review, permits and inspections for Phase 1 of the OpenAI data center. The board chairman stepped out of the vote because he works for Georgia Power.
    • Nov 3, 2026
      County commissioners voted unanimously to table the Project Camellia site plan until Nov. 17. They asked for a written promise of a 20-foot earthen berm along Hodgeville Road and answers on wetlands. The developer's plan now shows six buildings and about 30,000 gallons of water a day.
    • Nov 6, 2026
      Three residents sued OpenAI, its affiliate Octans GA LLC, the county development authority, the county commissioners and others in Effingham County State Court. They claim fraud, hiding facts and a state RICO violation, and ask for money damages.

    Local votes and rules

    ⏸️ Pause on new data centers

    Effingham County commissioners have a data center moratorium on their Nov. 17, 2026 agenda (5 p.m., county complex in Springfield). It would pause land use changes, rezonings, special use permits and public hearings for data centers while staff write a data center ordinance. The same meeting is expected to take up the OpenAI site plan.

    Nov 17, 2026

    ⚖️ Court case

    Three residents sued OpenAI, its affiliate Octans GA LLC, the county development authority, the county commissioners and others over the Project Camellia data center. They claim fraud, hiding facts and a state RICO violation, and ask for money damages and a jury trial. The claims have not been proven in court.

    Nov 6, 2026

    ⚖️ Court case

    Five residents and the group One Hundred Miles sued the county's development authority. They say it did not give proper notice or a real agenda before the July vote that tied county land to OpenAI's company and gave it a 50% property tax break. They ask a judge to throw out those deals.

    Sept 21, 2026

    📌 Other

    The county took the OpenAI data center site plan off its September 15 meeting agenda to give staff more time to review it. No new vote date was given in the report.

    Sept 15, 2026

    ⚖️ Court case

    Three residents sued Effingham County. They say the county skipped a required public hearing when it changed its industrial zoning to allow data centers with no conditions. That change cleared the way for the planned OpenAI data center near Rincon. They ask the court to throw out the change.

    Sept 3, 2026

    🤝 Agreement with the company

    The county's development authority approved a tax break deal for OpenAI's planned $20 billion data center (Project Camellia) on 1,440 acres near Rincon. OpenAI gets a 50% property tax cut for 15 years, worth about $870 million, and locks in the 2026 tax rate. It must report each year and meet goals of $20 billion invested and 400 jobs at first.

    July 21, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. $20 billion OpenAI data center to open in Effingham County · The Current GA · July 22, 2026
    2. Anatomy of a secret Coastal Georgia data center deal · The Current GA · Aug 8, 2026
    3. PSC boosts safeguards in Georgia Power's massive contract with OpenAI · The Current GA · Aug 27, 2026
    4. How much water will Effingham's OpenAI data center need? A lot - but not on site. · The Current GA · Sept 1, 2026
    5. Citizen-led lawsuit challenges zoning for OpenAI Georgia data center · The Current GA · Sept 3, 2026
    6. Effingham postpones OpenAI data center site plan review · The Current GA · Sept 14, 2026
    7. New lawsuit alleges unfair secrecy around Effingham data center · The Current GA · Sept 21, 2026
    8. DRI #4801 Project Camellia - application summary · Georgia Department of Community Affairs · July 29, 2026
    9. DRI #4801 Project Camellia - additional information form · Georgia Department of Community Affairs · July 29, 2026
    10. Oct. 21: County commissioners voted to move forward on data center, contractor hired for phase 1 · Savannah Business Journal · Oct 21, 2026
    11. Public Notice SAS-2026-00872 (Octans GA, LLC) · U.S. Army Corps of Engineers, Savannah District · Oct 5, 2026
    12. Effingham County to Vote on OpenAI Data Center Plan on Election Day · Effingham Herald · Oct 2026
    13. Effingham County delays vote on OpenAI data center site plan · WTOC · Nov 5, 2026
    14. Effingham County residents sue OpenAI, county officials over Project Camellia data center · WTOC · Nov 9, 2026
    15. Effingham County to decide on OpenAI data center (Savannah Morning News, republished) · Savannah Morning News · Nov 16, 2026

    See something wrong? Tell us and we'll fix it.