Approved, not built yet
Stream Data Centers Winston campus (SDC ATLA)
Also called: Stream Data Center, SDC ATLA
Stream Data Centers plans nine data center buildings and two substations on about 243 acres in rural Winston. County commissioners approved it 3-2 in July 2025 against their staff's advice. The company says it will pay more than $55 million a year in taxes and not seek a tax break.
Where things stand: Rezoning approved 3-2 in July 2025, overruling staff and the planning board.
๐ Latest update (July 2025): Douglas County commissioners approved the rezoning 3-2, minutes after the planning board voted 4-1 to recommend denial.
What we know
- ๐ WhereAbout 243 acres framed by Veterans Memorial Highway and North Baggett and Barrow roads, in Winston, Unincorporated Douglas County, Douglas County
- ๐ข CompanySDC ATLA, LLC
- ๐๏ธ Owned byStream Data Centers
- ๐ณ Size243 acres
- ๐ Where the power comes fromPlans include two utility substations.
- ๐ง WaterDouglasville-Douglas County Water & Sewer Authority ยท 18,000 gallons a day
- ๐ต Cost$4.5 billion
- ๐ธ Tax breaksThe developer said it will not ask for a tax break (abatement).
- ๐ท Jobs promised220
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power will the campus use? ๐ I'll find out
- Who is the end user? ๐ I'll find out
- When will construction start? ๐ I'll find out
What happened so far
- Nov 26, 2024Stream filed nine data center buildings (2.7 million square feet) for state regional review (DRI #4334).
- July 2025Douglas County commissioners approved the rezoning 3-2, minutes after the planning board voted 4-1 to recommend denial.
๐ฐ๏ธ See it from above
An aerial photo of the area.
Photos: USGS The National Map.
Where this comes from
- DRI #4334: Stream Data Center (Development of Regional Impact filing) ยท Georgia Department of Community Affairs ยท Nov 26, 2024
- DRI #4334: Stream Data Center, Additional Information Form ยท Georgia Department of Community Affairs ยท Nov 26, 2024
- Commission overrules planner again, OKs second Winston data center ยท Douglas County Sentinel ยท July 11, 2025
- DRI #4334 Initial Information Form: Stream Data Center (location field) ยท Georgia Department of Community Affairs ยท Oct 7, 2026
- Douglas County tax parcel 0166-025-0005/0006 (county parcel map service) ยท Douglas County ยท Oct 7, 2026