Approved, not built yetBig (AI-size): 583.6 acres

Project Splice technology campus outside Cordele

Also called: Project Splice, Cordele Technology Campus, Red Wolf data center

A data center campus of up to seven buildings is planned on about 584 acres just east of Cordele. Crisp County approved the rezoning in June 2025. Filings value it at $6 billion, and county staff said it would use about 300,000 gallons of water a day. By August 2026 a new developer, Premier Data Center Development, was leading the project, and residents met to talk about it.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Crisp County Board of Commissioners (for land outside city and town limits).

Where things stand: Approved, not built yet Crisp County rezoned 583.62 acres for the data center on June 10, 2025. A new developer, Premier Data Center Development, now leads the project.

❓ 5 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Aug 2026): Residents met at Midway Church about the project, now led by Premier Data Center Development.

What we know

  • 📍 WhereLand fronting Cemetery Road, Old Nesbit Road and Ninth Street, east of Cordele, less than 1 mile from I-75 Exit 102, Unincorporated Crisp County, Crisp County
  • 🏢 CompanyPremier Data Center Development (earlier: Red Wolf DCD Properties LLC)
  • 🌳 Size583.62 acres
  • 🔌 Where the power comes fromCrisp Electric said it has power for the first phase. The developer said it will pay for power upgrades.
  • 💧 WaterCity of Cordele water and sewer · 300,000 gallons a day
  • 💵 Cost$6 billion
  • 👷 Jobs promised180

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will the campus use? 🙋 I'll find out ·
  • Who is the end user (tenant)? 🙋 I'll find out ·
  • Will new high-voltage power lines or a new substation be built near homes? 🙋 I'll find out ·
  • How many diesel backup generators will there be? 🙋 I'll find out ·
  • Were any tax breaks given, or agreements to keep plans private (NDAs) signed? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • March 2025
      Red Wolf DCD Properties filed a state regional impact review (DRI) for seven 300,000 square foot buildings and a substation, built in phases from 2029 to 2033.
    • April 3, 2025
      The Middle Flint Regional Commission found the project in the best interest of the region (state regional impact review).
    • May 13, 2025
      Crisp County commissioners held a public hearing; nearby residents spoke against it.
    • June 10, 2025
      Commissioners voted unanimously to rezone 583.62 acres from rural residential to general commercial, with conditions.
    • Aug 2026
      Residents met at Midway Church about the project, now led by Premier Data Center Development.

    Local votes and rules

    🗺️ Zoning change

    Crisp County commissioners unanimously rezoned about 584 acres off Cemetery Road and Ninth Street from rural residential to general commercial for a data center by Red Wolf Properties, with a list of conditions. Staff estimated water use at about 300,000 gallons a day.

    June 10, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. 2.1 million sq ft technology campus proposed in southern Georgia · Data Center Dynamics · March 7, 2025
    2. Residents voice opposition to rezoning for data center · Cordele Dispatch · May 20, 2025
    3. Rezoning approved for Crisp County data center · Cordele Dispatch · June 11, 2025
    4. Congressional candidate addresses citizen concerns over data center · Cordele Dispatch · Aug 28, 2026
    5. DRI #4390 Project Splice - application summary · Georgia Department of Community Affairs · March 10, 2025
    6. DRI #4390 Project Splice - additional information form · Georgia Department of Community Affairs · March 10, 2025

    See something wrong? Tell us and we'll fix it.