Being built

Serverfarm data center with on-site gas power (Covington)

Also called: Serverfarm Hazelbrand Road

Serverfarm is building a data center in Covington that would run on its own gas-fired power plant built next door by VoltaGrid. Georgia's Environmental Protection Division stopped the power plant in July 2026 for building without an air permit. In September the state fined the two companies a total of $42,500, and they may keep building under stricter pollution limits.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Covington City.

Where things stand: Being built Under construction. In Sept. 2026 the state fined Serverfarm $31,000 and VoltaGrid $11,500 for building before they had air permits; both now have permits and can keep building under stricter limits.

❓ 2 open questions about it: see below.

Last checked Oct 12, 2026.

🕒 Latest update (Sept 30, 2026): Georgia EPD published consent orders fining Serverfarm $31,000 and VoltaGrid $11,500 for starting construction before getting permits. The final permit treats the plant and data center as one pollution source and lets VoltaGrid run no more than 30 of its 33 engines at once.

What we know

  • 📍 Where10835 Hazelbrand Road NE, Covington (97 acres with an existing warehouse), Covington, Newton County
  • 🏢 CompanyServerfarm
  • 🔌 Where the power comes fromIts own 'pop-up' gas power plant (dozens of gas engines) built next door by VoltaGrid, instead of the grid.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts is the data center? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked USGS aerial imagery of the site (33.598794, -83.835402): the old pin sat on a shopping-strip crossroads, not on a 97-acre warehouse site, so it was removed.

    What happened so far

    • June 29, 2026
      Georgia EPD inspectors found 37 diesel backup generators being installed at the Serverfarm site and gas engines at the VoltaGrid plant. EPD issued Serverfarm its air permit the same day.
    • July 2026
      Georgia EPD sent notices of violation to VoltaGrid and Serverfarm and ordered the gas power plant to stop construction, saying generators were built without a permit.
    • Sept 30, 2026
      Georgia EPD published consent orders fining Serverfarm $31,000 and VoltaGrid $11,500 for starting construction before getting permits. The final permit treats the plant and data center as one pollution source and lets VoltaGrid run no more than 30 of its 33 engines at once.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Georgia agency orders data center's 'pop-up' power plant to halt construction · The Atlanta Journal-Constitution · July 8, 2026
    2. OpenStreetMap: Hazelbrand Road · OpenStreetMap contributors · Oct 7, 2026
    3. Serverfarm: Covington, GA (10835 Hazelbrand Rd NE, 97 acres, existing 498,960 sq ft warehouse) · Baxtel · Oct 8, 2026
    4. Georgia fines 2 companies over data center, power plant permit violations · Atlanta News First · Oct 6, 2026
    5. State fines companies for 'pop-up' power plants for data center · The Atlanta Journal-Constitution · Oct 8, 2026
    6. Data center, 'pop-up' power plant fined just $41,500 after starting without permit · WSB-TV · Oct 6, 2026