ProposedBig (AI-size): 200 megawatts

Project Indo (DataBank)

Also called: Project Indo

DataBank wants to build a 200-megawatt data center campus, about 1.1 million square feet, on 69 acres of an old factory site in Cartersville. The filing values it at $2.4 billion and says the first part could open around 2032. It would need a rezoning from the city.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Cartersville City.

Where things stand: Proposed Filed for state review in June 2026. Needs a rezoning and a variance from the city.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (July 15, 2026): The regional commission issued its finding on the project.

What we know

  • 📍 Where218 Industrial Park Road (current CETCO manufacturing site), Cartersville, Bartow County
  • 🏢 CompanyDataBank Holdings Ltd
  • 🏛️ Owned byDataBank
  • 🌳 Size69 acres
  • ⚡ Power it needs200 megawatts (about as much as 160,000 homes)
  • 🔌 Where the power comes fromCartersville Electric System and MEAG Power. The filing asks for about 288 megawatts from the grid. The site is close to a substation.
  • 💧 WaterCity of Cartersville · 5,034 gallons a day
  • 💵 Cost$2.4 billion
  • 👷 Jobs promised60

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • When will Cartersville vote on the rezoning? 🙋 I'll find out ·
  • Who will use the data center? 🙋 I'll find out ·
  • Will it use diesel backup generators, and how many? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • June 19, 2026
      City of Cartersville filed the project for state regional review (DRI #4761). It asks for a rezoning and a variance.
    • July 15, 2026
      The regional commission issued its finding on the project.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4761: Project Indo (Development of Regional Impact filing) · Georgia Department of Community Affairs · June 19, 2026
    2. DRI #4761: Project Indo, Additional Information Form · Georgia Department of Community Affairs · June 19, 2026
    3. DataBank files for 200MW data center campus outside Atlanta, Georgia · Data Center Dynamics · 2026
    4. DRI #4761 Initial Information Form: Project Indo (location field) · Georgia Department of Community Affairs · Oct 7, 2026
    5. Bartow County tax parcel C059-0001-001 (county parcel map service) · Bartow County · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.