Brantley County leaders say someone wants to buy the old landfill site for a data center, but no formal plan has been filed. Commissioners considered changing the land use rules to allow data centers and put off the vote after strong public pushback.
Where things stand: No formal proposal has been filed. In January 2026 the county said a person interested in building a data center (described as a Microsoft data center) had approached it about buying the land. The county's vote on allowing data centers in light industrial zones was postponed.
🕒 Latest update (June 2026): Residents gave commissioners a petition with 1,310 signatures against a data center.
What we know
- 📍 WhereLand where Brantley County Development Partners, LLC proposed a landfill in 2016, Unincorporated Brantley County, Brantley County
- 🔌 Where the power comes fromThe county manager said the data center would make its own power on site and not drain Okefenokee EMC.
- ❄️ CoolingA lined pond with water recirculated on site was described
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who wants to buy the landfill tract, and is Microsoft really involved? 🙋 I'll find out
- Will Brantley County vote to allow data centers in light industrial zones, and when? 🙋 I'll find out
- How much power and water would the data center use, and would it build its own power plant? 🙋 I'll find out
What happened so far
- Jan 9, 2026The county manager said commissioners met with a person interested in a data center on the landfill tract, and that an offer to buy the land was 'in the works.'
- Jan 20, 2026Commissioners held a called hearing on adding data centers as a special exception in light industrial zones. About 70 people came.
- Feb 2026The commission postponed its decision on the data center zoning change.
- June 2026Residents gave commissioners a petition with 1,310 signatures against a data center.
Drag the slider to compare the land before and now.
Where this comes from
- BCDP group are possibly open to selling off landfill property · Brantley Beacon / Blackshear Times · Jan 13, 2026
- Commissioners hear from residents concerning re-zoning · Brantley Beacon / Blackshear Times · Jan 27, 2026
- Brantley County Commission postpones data center decision · Brantley Beacon / Blackshear Times · Feb 10, 2026
- Citizens fill commission meeting to talk about data center · Brantley Beacon / Blackshear Times · June 9, 2026
See something wrong? Tell us and we'll fix it.