Project Eisenhower is a planned six-building data center campus, about 2.15 million square feet, off Gordon Highway in Augusta. It replaces an earlier T5 plan for 200 megawatts on the same site. T5 says it is no longer involved.
Where things stand: Revised plan filed for state review in March 2024; the regional commission found it in the region's interest. T5 left the project.
๐ Latest update (March 27, 2024): Eagle South filed a revised six-building, 2.15 million square foot campus for state regional review (DRI #4171).
What we know
- ๐ WhereOff Gordon Highway (earlier plan at 2111 Powell Road), Augusta, Richmond County
- ๐ข CompanyEagle South, LLC
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer behind Eagle South LLC and who is the end user? ๐ I'll find out
- Is construction under way? ๐ I'll find out
- How much power and water will it use? ๐ I'll find out
What happened so far
- March 27, 2024Eagle South filed a revised six-building, 2.15 million square foot campus for state regional review (DRI #4171).
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
Photos: USGS The National Map.
Where this comes from
- DRI #4171: Project Eisenhower (Development of Regional Impact filing) ยท Georgia Department of Community Affairs ยท March 27, 2024
- Plans filed to expand former T5 campus site in Augusta, Georgia ยท Data Center Dynamics ยท 2024