Project Eisenhower data center (former T5@Augusta site)
Also called: T5@Augusta
Project Eisenhower is a planned six-building data center campus, about 2.15 million square feet, off Gordon Highway in Augusta. It replaces an earlier T5 plan for 200 megawatts on the same site. T5 says it is no longer involved.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Richmond County Board of Commissioners (for land outside city and town limits).
Where things stand: Proposed Revised plan filed for state review in March 2024; the regional commission found it in the region's interest. T5 left the project.
❓ 3 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (March 27, 2024): Eagle South filed a revised six-building, 2.15 million square foot campus for state regional review (DRI #4171).
What we know
- 📍 WhereOff Gordon Highway (earlier plan at 2111 Powell Road), Augusta-Richmond County, Richmond County
- 🏢 CompanyEagle South, LLC
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer behind Eagle South LLC and who is the end user? 🙋 I'll find out ·
- Is construction under way? 🙋 I'll find out ·
- How much power and water will it use? 🙋 I'll find out ·
What happened so far
- March 27, 2024Eagle South filed a revised six-building, 2.15 million square foot campus for state regional review (DRI #4171).
Local votes and rules
📜 Data center rules
Augusta commissioners adopted a 29-page data center ordinance on second reading by a 6-5 vote on Oct. 6, 2026. It keeps data centers out of homes and farm zones, sets rules by project size, requires closed-loop cooling and bans private wells for cooling. A push for more changes and expert testimony was blocked; changes must now come as formal amendments.
Drag the slider to compare the land before and now.
Where this comes from
- DRI #4171: Project Eisenhower (Development of Regional Impact filing) · Georgia Department of Community Affairs · March 27, 2024
- Plans filed to expand former T5 campus site in Augusta, Georgia · Data Center Dynamics · 2024
- Augusta, GA - Official Website · Augusta-Richmond County consolidated government · Oct 10, 2026
See something wrong? Tell us and we'll fix it.