ProposedBig (AI-size): 600 megawatts

Nixon Technology Center data center campus (Augusta)

Also called: Nixon Technology Campus, DRI #4853

3G Investments wants to build a seven-building data center campus on land near Four H Club Road and Mike Padgett Highway in southeast Augusta, close to the airport. The state filing describes 3.34 million square feet on about 388 acres. Nothing is approved. The Planning Commission hearing was moved from Nov. 2 and is reported to be set for Nov. 23, 2026.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Monday, November 23, 2026 (time not announced)

Augusta Planning Commission hearing

📍 Augusta (place not given in the report)

Special called meeting.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Proposed The Nov. 2 Planning Commission hearing was put off at the developer's request. The League of Women Voters of the CSRA says a special Planning Commission hearing is now set for Nov. 23, 2026. The state regional review (DRI) is due to finish about Nov. 29.

❓ 9 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 2026): The Nov. 2 Planning Commission hearing was put off to Dec. 7 at the developer's request, then moved up to a special hearing on Nov. 23, according to the League of Women Voters of the CSRA.

What we know

  • 📍 Where1550 and 1538 Four H Club Road and 3806 Mike Padgett Highway, southeast Richmond County near Augusta Regional Airport, Augusta-Richmond County, Richmond County
  • 🏢 Company3 G Investments, LLC
  • 🌳 Size388 acres
  • ⚡ Power it needs600 megawatts (about as much as 480,000 homes)
  • 🔌 Where the power comes fromGeorgia Power; the filing says turbine generators with battery storage may be used for backup
  • 💧 WaterAugusta Utilities
  • ❄️ Coolingclosed-loop system (per the developer's state filing)
  • 👷 Jobs promised40

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is the end user (tenant)? 🙋 I'll find out ·
  • How much water will it use per day, and what cooling system will it have? 🙋 I'll find out ·
  • Do Augusta's new data center rules (adopted Oct. 6, 2026) apply to this application, which was filed Sept. 28? 🙋 I'll find out ·
  • The news report says about 383 acres; the state filing says about 388 acres. Which is right? 🙋 I'll find out ·
  • The developer's state filing lists about 600 MW of peak power. Has Georgia Power agreed to serve that much? 🙋 I'll find out ·
  • How much water will the closed-loop cooling system need to fill and top up? 🙋 I'll find out ·
  • When will the Augusta Commission vote on rezoning Z-26-18 and special exception SE-26-22? 🙋 I'll find out ·
  • Will residents get another chance to speak after the state regional review ends and before the Planning Commission votes? 🙋 I'll find out ·
  • Will Augusta publish an official notice for the Nov. 23, 2026 Planning Commission hearing, and where will it be held? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 26, 2026: We checked the state DRI Part 2 form: Georgia Power, about 600 MW peak load, closed-loop cooling, Augusta Utilities water, 40 full-time jobs, $3 billion build-out value.

    What happened so far

    • Sept 28, 2026
      3G Investments asked Augusta to rezone about 383 acres and grant a special exception for a seven-building data center campus. The land is owned by the Nixon Trusts.
    • Oct 12, 2026
      Augusta started a state regional impact review (DRI #4853) for a 3.34 million-square-foot data center campus on about 388 acres. The filing lists build-out in 2028 and 2029.
    • Oct 27, 2026
      Augusta's city attorney wrote that applications filed after the first reading of the new data center rules are covered by them, and that the Nixon application appeared to meet them. Planning staff had not finished its review.
    • Oct 30, 2026
      The regional commission started taking comments in the state regional review (DRI #4853). The state list shows the review should finish about Nov. 29, 2026.
    • Nov 2026
      The Nov. 2 Planning Commission hearing was put off to Dec. 7 at the developer's request, then moved up to a special hearing on Nov. 23, according to the League of Women Voters of the CSRA.

    Local votes and rules

    📜 Data center rules

    Augusta commissioners adopted a 29-page data center ordinance on second reading by a 6-5 vote on Oct. 6, 2026. It keeps data centers out of homes and farm zones, sets rules by project size, requires closed-loop cooling and bans private wells for cooling. A push for more changes and expert testimony was blocked; changes must now come as formal amendments.

    Oct 6, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4853: Nixon Technology Center · Georgia Department of Community Affairs · Oct 12, 2026
    2. DRI #4853: Nixon Technology Center, Initial Information Form · Georgia Department of Community Affairs · Oct 12, 2026
    3. 383-acre data center campus proposed off Mike Padgett Highway · WRDW News 12 · Oct 14, 2026
    4. DRI #4853: Nixon Technology Center, Information Form Part 2 · Georgia Department of Community Affairs · Oct 12, 2026
    5. Augusta's Data Center Ordinance Faces Its First Test · League of Women Voters of the Coastal Savannah River Area (Civic Dispatch) · Oct 28, 2026
    6. Augusta's New Data Center Rules Face First Test · League of Women Voters of the CSRA · Nov 12, 2026

    See something wrong? Tell us and we'll fix it.