Unnamed hyperscale data center application (Kanner Highway, Martin County)
Someone applied to Martin County to build a hyperscale data center off Kanner Highway, west of I-95. The application came in one day before the county started a one-year pause on new large data centers, so the pause does not stop it. The developer has not been named.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Martin County Board of County Commissioners (for land outside city and town limits).
Where things stand: Proposed Application filed with Martin County on Oct 12, 2026, one day before the county's moratorium hearing. The county says it is not covered by the new one-year pause.
- Oct 27, 2026: Unincorporated Martin County, Martin County: moratorium adopted Source
❓ 4 open questions about it: see below.
Last checked Nov 1, 2026.
🕒 Latest update (Oct 27, 2026): County commissioners adopted a one-year pause on new large data centers. News reports say the hyperscale application off Kanner Highway is not affected because it was filed first.
What we know
- 📍 Whereoff Kanner Highway, west of Interstate 95, unincorporated Martin County, Unincorporated Martin County, Martin County
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer, and which company would use the data center? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or application number helps. 🙋 I'll find out ·
- How many megawatts and how much water would it use? 🙋 I'll find out ·
- Has the county found the application complete, and when will it go to a public hearing? 🙋 I'll find out ·
What happened so far
- Oct 12, 2026Martin County received an application for a data center in unincorporated Martin County, one day before the first hearing on a data center moratorium.
- Oct 27, 2026County commissioners adopted a one-year pause on new large data centers. News reports say the hyperscale application off Kanner Highway is not affected because it was filed first.
Local votes and rules
⏸️ Pause on new data centers
At the second hearing, county commissioners voted 4-0 for a one-year pause on new large data centers in unincorporated Martin County. The county will use the year to write rules. A hyperscale application off Kanner Highway, filed before the vote, is not covered.
⏸️ Pause on new data centers
County commissioners moved a one-year pause on data centers forward at the first of two required public hearings. It is not final until the second vote. We did not find a confirmed date for that vote.
⏸️ Pause on new data centers
County commissioners voted 4-1 to have staff bring back a one-year data center pause. The county attorney called the legal question a gray area because of two state laws. We did not find a final vote.
Drag the slider to compare the land before and now.
Where this comes from
- Martin County advances proposed data center moratorium · CBS12 · Oct 13, 2026
- Martin County approves 1-year pause on new data center development · WPTV · Oct 27, 2026