USA โ€บ Florida โ€บ Martin County โ€บ Indiantown Village
Approved, not built yet

Tesoro Groves (FPL land, Indiantown)

Also called: Tesoro Groves PUD

Florida Power & Light got about 5,700 acres in Indiantown rezoned for future development. FPL lists a data center among possible uses but says no project has been approved. Any project would need its own site plan and hearings.

โœ” ConfirmedSourceLast checked: Oct 2026

Where things stand: Village approved FPL's rezoning in April 2026. FPL says it is a planning framework, not a specific project; a data center is one possible use.

๐Ÿ•’ Latest update (July 2, 2026): The lawsuit was voluntarily dismissed with prejudice.

What we know

  • ๐Ÿ“ WhereKanner Highway, west of Warfield Boulevard, Indiantown, Martin County
  • ๐Ÿข CompanyFlorida Power & Light
  • ๐ŸŒณ Size5,722 acres
  • ๐Ÿ”Œ Where the power comes fromFPL owns the land; solar panels and a power line are already on the property.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Does FPL have a data center customer for Tesoro Groves? ๐Ÿ™‹ I'll find out
  • Are 'Project Growler' and 'Project Beskar', mentioned by residents, planned on this land? ๐Ÿ™‹ I'll find out
  • Where is the 5,722-acre Tesoro Groves land, and which part could hold a data center? A map or parcel list from the village helps. ๐Ÿ™‹ I'll find out

What happened so far

  • Feb 12, 2026
    Village Council gave final approval to annex the FPL land, according to FPL.
  • April 30, 2026
    Village Council unanimously approved the planned unit development zoning.
  • May 25, 2026
    A local nonprofit and residents sued the village and FPL over the annexation and rezoning.
  • July 2, 2026
    The lawsuit was voluntarily dismissed with prejudice.

Local votes and rules

๐Ÿ“Œ Other

Village council voted 4-1 against pausing data center applications for now and asked for a new legal opinion and stronger wording. A lawyer for the Silver Fox 606 project said it would sue if the village paused applications.

Sept 1, 2026

โš–๏ธ Court case

A local nonprofit and residents sued the village and FPL over annexing and rezoning the 5,722-acre Tesoro Groves land, where a data center is one possible use. The suit was voluntarily dismissed with prejudice (it cannot be refiled).

July 2, 2026
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

20182025
We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something