Approved, not built yet

Stonebridge hyperscale AI data center campus (Fort Meade)

Stonebridge plans a 4.4 million square foot AI data center campus on about 1,300 acres in Fort Meade. It would need about 1.2 gigawatts of power. The city approved it 5-0 in April 2026, but state officials question the water plan and residents have sued.

✔ ConfirmedSourceLast checked: Oct 2026

Where things stand: City approved rezoning and a tax break in 2025 and a 20-year development agreement in April 2026. Residents sued; state water permits still needed.

🕒 Latest update (June 2026): Nearby residents sued the city in Polk County, saying owners got no proper notice and the project breaks the city's comprehensive plan.

What we know

  • 📍 WhereFormer phosphate mine land west of U.S. 98 in northwest Fort Meade (main parcel 25-31-16-000000-012040), Fort Meade, Polk County
  • 🏢 CompanyStonebridge
  • 👤 Built forunknown (developer says the tenant or buyer will likely not be known until construction)
  • 🌳 Size1,300 acres
  • ⚡ Power it needs1,200 megawatts (about as much as 960,000 homes)
  • 🔌 Where the power comes fromNeeds about 1.2 gigawatts of power, plus 100% backup generators. Utility not named in the sources.
  • 💧 WaterCity of Fort Meade water from the Upper Floridan Aquifer · 50,000 gallons a day
  • ❄️ Coolingclosed-loop cooling, no discharge (per development agreement)
  • 💵 Cost$2.6 billion
  • 💸 Tax breaksPolk County approved about $140 million in tax breaks over 10 years. The city also gave a tax break with the 2025 rezoning. Stonebridge pays $10 million up front, which the state says is an advance on future property taxes.
  • 👷 Jobs promised500

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2025
    Fort Meade approved a zoning change and a tax break for Stonebridge.
  • March 2026
    City commission delayed its vote on the development agreement after residents protested.
  • April 2026
    The state Commerce Secretary sent a letter calling the water estimate 'woefully underestimated'. The water district warned the city cannot use its current permit for the project.
  • April 7, 2026
    Planning commission voted unanimously to recommend the 20-year development agreement.
  • April 14, 2026
    City commissioners voted unanimously (5-0) to approve the 20-year development agreement.
  • June 2026
    Nearby residents sued the city in Polk County, saying owners got no proper notice and the project breaks the city's comprehensive plan.

Local votes and rules

🗳️ Election

A residents' group turned in petitions to recall the mayor, vice mayor and one commissioner, mainly over the data center vote. Signatures must be checked, and more signatures are needed before a recall election can be set.

July 16, 2026

⚖️ Court case

Nearby residents sued the city over its approval of the data center. They say owners did not get proper notice of hearings and that the project breaks the city's comprehensive plan. They want a court review of the decision.

June 2026

✅ Approved

City commissioners voted unanimously to approve a 20-year development agreement for the Stonebridge hyperscale data center campus. Residents had asked for a pause instead.

April 14, 2026
🛰️ See it from above

Drag the slider to compare the land before and now.

20182025