Send us a tip
Stopped or cancelledBig (AI-size): 300 megawatts

NE Edge data center at Millstone nuclear plant

Also called: NE Edge Waterford, NE Edge-Waterford LLC, Millstone data center

NE Edge wanted to build two very large data center buildings on the Millstone nuclear plant property and buy power directly from the plant. The state Siting Council would not approve the needed site change in 2024, and the town says the deal ended in March 2026.

✔ ConfirmedSourceLast checked: Oct 8, 2026

What happens next?

Where things stand: Stopped or cancelled The town's fee deal with the developer ended in March 2026 after the developer defaulted. The state Siting Council never approved the site change it needed.

❓ 2 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (March 17, 2026): Waterford's First Selectman announced the project had ended because NE Edge-Waterford LLC defaulted on the host fee agreement.

What we know

  • 📍 WhereOn Dominion Energy's Millstone Power Station land, off Rope Ferry Road, Waterford, Southeastern Connecticut Planning Region
  • 🏢 CompanyNE Edge LLC
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
  • 🔌 Where the power comes fromPlanned to buy power straight from the Millstone nuclear plant next door.
  • 💸 Tax breaksHost fee deal with Waterford: about $231 million over 30 years instead of property taxes (deal ended March 2026).

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Did the town or the developer publish a formal notice that the host fee agreement ended? 🙋 I'll find out ·
  • Does Dominion or another developer still plan a data center at Millstone? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2023
      Waterford signed a host fee agreement with NE Edge (payments instead of property taxes).
    • Feb 2023
      NE Edge proposed two data center buildings totaling about 1.5 million square feet at Millstone.
    • July 28, 2023
      Dominion asked the state Siting Council to change the Millstone site boundary so the data center land could be split off (Petition 1586).
    • Jan 4, 2024
      The Siting Council declined to rule, saying it was too early because there was too little information about the data centers and their direct link to Millstone.
    • March 17, 2026
      Waterford's First Selectman announced the project had ended because NE Edge-Waterford LLC defaulted on the host fee agreement.

    Local votes and rules

    🤝 Agreement with the company

    Waterford signed a host fee deal with NE Edge for a data center at the Millstone nuclear plant (payments instead of normal property taxes). On March 17, 2026, the First Selectman said the project had ended because the developer broke the deal's terms.

    2023
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. NE Edge Proposes 1.5M Square Foot Data Center at Millstone in Waterford · CT Examiner · Feb 16, 2023
    2. Petition No. 1586 decision letter · Connecticut Siting Council · Jan 4, 2024
    3. Shoreline residents concerned with plan for large data center · WFSB · Jan 18, 2024
    4. CCWEL resources (project ended March 17, 2026) · Concerned Citizens of Waterford and East Lyme (resident group) · March 2026
    5. Tale of a defeated CT data center (opinion) · CT Mirror · April 15, 2026
    6. Connecticut Data Center Proposed Projects (2026 Summary) · Energize Connecticut · Aug 11, 2026

    See something wrong? Tell us and we'll fix it.