USA โ€บ Colorado โ€บ Weld County
Approved, not built yet

Global AI data center at the former Kodak/Carestream site

Also called: GlobalAI Windsor data center

Global AI plans a data center on 41 acres of the old Kodak/Carestream plant near Windsor, reusing a vacant factory building. Weld County approved the first phase, about 27.5 megawatts, in September 2026. The company has said it wants to grow to 1 gigawatt, but any bigger phase needs a new county review.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Weld County commissioners approved a special-use permit 5-0 in Sept 2026 for a first phase; building permits still needed.

๐Ÿ•’ Latest update (Sept 1, 2026): The Weld County planning commission found the plan met approval rules.

What we know

  • ๐Ÿ“ Where2000 Howard Smith Avenue W, former Carestream (Kodak) property near Windsor, Weld County
  • ๐Ÿข CompanyGlobal AI
  • ๐ŸŒณ Size41 acres
  • โšก Power it needs27.5 megawatts (about as much as 22,000 homes)
  • ๐Ÿ”Œ Where the power comes fromPoudre Valley Rural Electric Association (will-serve letter for 35 MW)
  • โ„๏ธ Coolingclosed-loop, air-cooled
  • ๐Ÿ‘ท Jobs promised200

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Dec 2025
    Global AI bought the 438-acre former Carestream property for about $15.6 million.
  • Sept 2026
    Weld County commissioners voted 5-0 to approve a special-use permit after a hearing that began Sept. 9.
  • Sept 1, 2026
    The Weld County planning commission found the plan met approval rules.

Local votes and rules

โœ… Approved

Weld County commissioners voted 5-0 to give Global AI a special-use permit for a 41-acre data center on the old Carestream site southeast of Windsor. The first phase is 27.5 megawatts; the company says it could grow to 1 gigawatt.

Sept 9, 2026

๐Ÿ—ณ๏ธ Public vote

Residents' group POWER got approval to collect signatures for a vote on the county's Global AI approval. It needs 9,103 valid signatures within 45 days. If it qualifies, commissioners must call a special election within 60 days.

Sept 2026

๐Ÿ“Œ Other

Weld County posted three stop-work orders (starting May 7, 2026) on Global AI's site for building without permits. On July 20 it sent an order to stop the illegal work by July 31. The county later approved the project's permit in September.

July 20, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Weld County commissioners approve permit for Global AI data center ยท KUNC / Colorado Newsline ยท Sept 12, 2026
  2. Global AI data center clears Weld County zoning hurdle ยท ConstructConnect ยท Sept 16, 2026
  3. GlobalAI data center company buys Carestream property ยท KUNC ยท Dec 23, 2025
  4. Xcel data center plan faces pushback from residents and advocates ยท Colorado Public Radio ยท Aug 26, 2026