USA › Ohio › Franklin County › Grove City City

1 data center project in Grove City City

Who decides here: the City Council of Grove City City votes on zoning. The Franklin County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Grove City City

Nearby (within 15 miles)

Local votes and rules

🗳️ Public vote

Voters approved Issue 28, about 55% to 45%. It changes the city charter so that very large projects (such as over 50 acres, over 20 megawatts of power, or over 500,000 gallons of water a day) need a citywide vote. Results are unofficial until the county elections board certifies them (expected in late November 2026).

Nov 3, 2026Source

🗳️ Public vote

Voters will decide a city charter change that would require a citywide vote on each new large data center before council can approve it. A data center is proposed in Grove City.

Nov 3, 2026Source

⏸️ Pause on new data centers

City council passed a one-year pause (moratorium) on new data centers. It is set to end in June 2027.

June 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Grove City City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Grove City City. Nothing else.

⚡ Your electric company

Depending on where you live in Grove City City: Ohio Power Co. (company) or City of Columbus (run by the town).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.

🙋 Open tasks here

  • Is the Rensch Road land inside Grove City or still in Jackson or Pleasant township?
  • Will the developer challenge the Grove City pause?
  • How much power and water would the campus need?
  • Would the Rensch Road data center now need a citywide vote under Issue 28?