No project in North Hampton Village, but 2 nearby
Who decides here: the Village Board of North Hampton Village votes on zoning. The Clark County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Urbana Technology Hub (Thor Equities data center)
Urbana, Champaign County
🕒 Nov 3, 2026: Urbana voters approved a charter ban on data centers except small, low-power ones, with …
Being builtabout 13 miles away5C AI data center at Prime Ohio Corporate Park (Springfield)
Springfield, Clark County
for Vultr (AI cloud cluster with AMD chips) and Crusoe
🕒 July 2026: Springfield approved a six-month pause on new very large (hyperscale) data centers. This…
Local votes and rules
🗺️ Zoning change · Clark County
County commissioners changed county zoning rules so data centers are only allowed, with special approval (conditional use), in heavy industrial (I-2) zones. None of the townships under county zoning has any I-2 land, so a developer would first need a rezoning. Ohio Capital Journal counts this as an effective ban.
What you can do
- Get told first.
We'll email you if anything changes in North Hampton Village. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Ohio Edison Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.