Being builtBig (AI-size): Described as an AI or hyperscale project in the sources

5C AI data center at Prime Ohio Corporate Park (Springfield)

Also called: OH5C, Former LexisNexis data center, Vultr Springfield AI cluster, Crusoe Springfield

5C Group is turning the old LexisNexis data center in Springfield into a 75-megawatt AI data center, growing it from 67,000 to 214,000 square feet. Vultr and Crusoe will run AI computers there. It plans 19 diesel backup generators.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Springfield City.

Where things stand: Being built Being rebuilt and expanded. The first 25 megawatts were due to run by the end of September 2026.

❓ 1 open question about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (July 2026): Springfield approved a six-month pause on new very large (hyperscale) data centers. This project was already underway.

What we know

  • 📍 WhereFormer LexisNexis data center, 601 Benjamin Drive, Prime Ohio Corporate Park, Springfield, Clark County
  • 🏢 Company5C Group
  • 👤 Built forVultr (AI cloud cluster with AMD chips) and Crusoe
  • ⚡ Power it needs75 megawatts (about as much as 60,000 homes)
  • 💧 WaterCity water, plus an on-site water reservoir to cut city water demand · 300,000 gallons a day
  • 🛢️ Diesel generators19
  • 💵 Cost$1.3 billion
  • 💸 Tax breaks15-year local enterprise zone tax break worth about $95 million, plus a 10-year state tax credit worth about $32 million.
  • 👷 Jobs promised160

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will 5C build its own power plant on site? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 9, 2025
      WYSO reported a new $1.3 billion data center in Springfield expected to open in early 2026.
    • July 2026
      Springfield approved a six-month pause on new very large (hyperscale) data centers. This project was already underway.

    Local votes and rules

    ⏸️ Pause on new data centers

    City council passed a six-month pause (moratorium) on new data centers. It is set to end in January 2027.

    July 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025