1 data center project in Urbana City
Who decides here: the City Council of Urbana City votes on zoning. The Champaign County may review big projects too.
In Urbana City
Nearby (within 15 miles)
Local votes and rules
π³οΈ Public vote
Voters will decide a city charter change that would ban data centers that use more than 7.5 megawatts of power. A data center is proposed, and the developer is suing the city.
βοΈ Court case
Developer Thor Equities sued the city in federal court after the city paused data centers and changed its zoning. Thor had planned a $1 billion, 460,000-square-foot data center near Ohio 55 and U.S. 68.
πΊοΈ Zoning change
City council repealed its 2025 rule that had allowed data centers in the M-1 manufacturing zone. News reports say this bans data centers in the city.
βΈοΈ Pause on new data centers
City council passed a one-year pause (moratorium) on new big data centers. A developer (Thor Equities) has sued the city in federal court. It is set to end in March 2027.
π€ Agreement with the company
City council approved a tax break deal (Community Reinvestment Area agreement) with Thor Equities for its planned data center.
What you can do
- Get told first.
We'll email you if anything changes in Urbana City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Urbana City: Dayton Power & Light Co. (company) or Pioneer Rural Electric Co-op, Inc. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.
π Open tasks here
- What has the court decided in Thor Equities' lawsuit against Urbana?
- Will the charter ban on very large data centers be on the ballot?