No project in Unincorporated Clark County, but 3 nearby
Who decides here: the Clark County Commission decides on zoning for land outside city and town limits.
Nearby (within 15 miles)
Townsite Solar 2 data center near Boulder City
Clark County
80 acres
π Sept 1, 2026: Interior Board of Land Appeals paused the project while the appeals are decided.
Proposedabout 7 miles awaySwitch Apex Industrial Park data center campus
North Las Vegas, Clark County
176 acres
π Sept 2026: County records show Switch bought about 176 more acres at Apex for about $196 million.
Reported in the news, not confirmed yet
Built & runningabout 11 miles awayGoogle Henderson data center
Henderson, Clark County
for Google
π Aug 27, 2024: Google said it would spend over $400 million in 2024 on its Storey and Clark County dataβ¦
Local votes and rules
π Other Β· Clark County
Clark County commissioners heard calls for a pause on data centers but took no action. They asked county staff to study how data centers affect county services and the county's land use code (Title 30). There is no moratorium in unincorporated Clark County.
β Approved Β· Clark County
Clark County commissioners, sitting as the zoning board, unanimously approved a 56,800-square-foot Switch data center on about 9 acres near Warm Springs Road, next to Switch's existing campus. Switch agreed to plant trees, pay for a sidewalk barrier, and use a closed-loop water system using under 1,000 gallons of public water a day.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Clark County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Unincorporated Clark County: Colorado River Comm of Nevada (public) or Southern California Edison Co. (company) or Wapa-- Western Area Power Administration (public) or Nevada Power Co. (company) or Overton Power District No 5 (public) or Valley Electric Assn, Inc. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Nevada.