No project in China Grove Town, but 2 nearby
Who decides here: the Town Council of China Grove Town votes on zoning. The Rowan County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Stopped or cancelledabout 11 miles away
Mooresville Technology Park data center (withdrawn)
Mooresville, Iredell County
400 acres
🕒 Aug 13, 2025: The developer withdrew its rezoning request after strong opposition.
Being builtabout 13 miles awayLong Ferry Road data center site
Rowan County, Rowan County
460 acres
🕒 April 21, 2026: Rowan County adopted a one-year data center moratorium; state law means it does not appl…
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town
What you can do
- Get told first.
We'll email you if anything changes in China Grove Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in China Grove Town: Duke Energy Carolinas, LLC (company) or City of Concord (run by the town).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in North Carolina.