Work has started on several hundred acres off Long Ferry Road for a power substation. The owner is a company tied to data center builder Edged, and the county says a data center is allowed there. Neighbors worry about generators, water use and noise.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Site work for a power substation began around March 2026. The county says the owner can build a data center there; no end user named.

πŸ•’ Latest update (April 21, 2026): Rowan County adopted a one-year data center moratorium; state law means it does not apply to this site.

What we know

  • πŸ“ WhereOff Long Ferry Road near I-85, outside Salisbury, Rowan County, Rowan County
  • 🏒 CompanyEDC Charlotte LLC (linked to data center builder Edged)
  • πŸ’Έ Tax breaksThe county says it offered no incentives.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • March 2026
    Site work began for a power substation.
  • April 21, 2026
    Rowan County adopted a one-year data center moratorium; state law means it does not apply to this site.

Local votes and rules

⏸️ Pause on new data centers

Rowan County commissioners unanimously passed a one-year pause on new data centers. Under state law it does not apply to the Long Ferry Road site, where work on a power substation had already started.

April 20, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Rowan County neighbors fight against suspected data center construction Β· WBTV Β· April 20, 2026
  2. Rowan County approves one-year moratorium on new data centers Β· WFAE Β· April 21, 2026

See something wrong? Tell us and we'll fix it.