Local votes and rules
⏸️ Pause on new data centers · Unincorporated Lowndes County
Lowndes County commissioners approved a 60-day pause on data center permit applications outside city limits on Aug. 25, 2026, so they can write permanent rules. Residents had asked for six months. County leaders said no data center had been approved or planned and no agreement to keep the plans private (NDA) had been signed.
🗺️ Zoning change · Unincorporated Lowndes County
Lowndes County rezoned about 719 acres on Coleman Road to light manufacturing with seven conditions. Data centers are allowed in that zone, so one could be built there, but the county says the rezoning is not an approval of any data center. The county has no data-center-specific ordinance yet and is studying one.
Find your town
In Georgia, cities and towns decide inside their limits. Outside them, the county decides.
Towns without a link have nothing reported yet. To see who decides there and your electric company, type your ZIP on the home page.