No project in Stockbridge City, but 11 nearby
Who decides here: the City Council of Stockbridge City votes on zoning. The Henry County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
TA Realty data center (East Tanners Church Road)
Unincorporated Clayton County, Clayton County
🕒 June 2025: Development Authority of Clayton County approved a tax break for the $959 million project.
Reported in the news, not confirmed yet
Proposedabout 9 miles awayRocky Creek Road data center (Red Wolf DCD Properties)
Unincorporated Henry County, Henry County
148.2 acres
🕒 May 3, 2024: A 1.25 million square foot data center filed for state regional review (DRI #4198).
Stopped or cancelledabout 9 miles awayEllenwood data center (PCC-DeKalb LLC)
Unincorporated DeKalb County, DeKalb County
95 acres
🕒 Aug 13, 2026: DeKalb County Board of Commissioners rejected the data center after almost a year of res…
Reported in the news, not confirmed yet
Proposedabout 10 miles awayFort Gillem data center campus (Digital Realty ATL15/ATL16)
Forest Park, Clayton County
97 acres
🕒 Dec 2025: Crews found old buried material with white phosphorus that smoked when it hit the air. W…
Proposedabout 10 miles awayStrickland Tract data center (Red Wolf DCD Properties)
Unincorporated Henry County, Henry County
249.8 acres
🕒 July 31, 2024: A 1.25 million square foot data center filed for state regional review (DRI #4251).
Stopped or cancelledabout 10 miles awayStillwater Technology Park (Lovejoy)
Lovejoy, Clayton County
🕒 Aug 6, 2026: The proposal was formally withdrawn at a special city council meeting.
Approved, not built yetabout 10 miles awayHenderson Farms data center campus (Hampton)
Hampton, Henry County
133 acres
🕒 March 24, 2026: A larger Henderson Farms plan with a data center campus and training facility was filed …
What you can do
- Get told first.
We'll email you if anything changes in Stockbridge City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Stockbridge City: Georgia Power Co. (company) or Snapping Shoals El Member Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.