No project in Tucker City, but 7 nearby
Who decides here: the City Council of Tucker City votes on zoning. The DeKalb County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Shadowbox Studios data center proposal
Unincorporated DeKalb County, DeKalb County
200 acres
🕒 Sept 9, 2026: DeKalb Zoning Board of Appeals affirmed the denial, leaving the matter to the courts.
Proposedabout 13 miles away1611 Ellsworth mixed-use project with data center
Atlanta, Fulton County
17.1 acres
🕒 Oct 21, 2025: The regional commission issued its finding on the project.
Approved, not built yetabout 14 miles awayDC BLOX Atlanta East data center (Farmer Road)
Unincorporated Rockdale County, Rockdale County
🕒 Jan 17, 2024: DC Blox filed three data center buildings (about 1 million square feet) for state region…
Proposedabout 14 miles awayRockdale Technology Park 1 (Sigman Road)
Unincorporated Rockdale County, Rockdale County
53 acres
🕒 Feb 15, 2024: Three data center buildings (837,500 square feet) filed for state regional review (DRI #…
Stopped or cancelledabout 14 miles awayEllenwood data center (PCC-DeKalb LLC)
Unincorporated DeKalb County, DeKalb County
95 acres
🕒 Aug 13, 2026: DeKalb County Board of Commissioners rejected the data center after almost a year of res…
Reported in the news, not confirmed yet
Stopped or cancelledabout 15 miles awayProject Rockforge data center campus (Grind Capital / MMM Acquisitions)
Unincorporated Rockdale County, Rockdale County
263 acres
🕒 Oct 6, 2026: Rockdale County commissioners denied four requests for Project Rock Forge, including a l…
Built & runningabout 15 miles awayEdged Atlanta data center campus (ATL01)
Atlanta, Fulton County
🕒 Aug 2024: Edged opened its first building, ATL01-1 (27 MW).
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Tucker City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Georgia Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.