1 data center project in Prichard City

Who decides here: the City Council of Prichard City votes on zoning. The Mobile County may review big projects too.

In Prichard City

Nearby (within 15 miles)

Local votes and rules

πŸ“Œ Other

Council moved to cancel the Edged data center's building permit and refund $224,000 in fees, saying the site plan skipped Planning Commission review. The developer's lawyer warned of a lawsuit, and the council sent the matter to the city attorney.

Aug 20, 2026Source

⏸️ Pause on new data centers

Council approved a six-month pause on new data centers, days after the city issued a building permit for the Edged data center on Telegraph Road.

Aug 4, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Prichard City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Prichard City. Nothing else.

⚑ Your electric company

Depending on where you live in Prichard City: Singing River Electric Cooperative (co-op (owned by its members)) or Alabama Power Co. (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Alabama.

πŸ™‹ Open tasks here

  • Is the building permit still valid?
  • How much power and water will the data center use?
  • Will the developer sue the city?